The Empirical Reality of IT Project Cost Overruns: Discovering A Power-Law Distribution

IF 5.9 2区 管理学 Q1 COMPUTER SCIENCE, INFORMATION SYSTEMS
B. Flyvbjerg, Alexander Budzier, Jong Seok Lee, M. Keil, Daniel Lunn, Dirk W. Bester
{"title":"The Empirical Reality of IT Project Cost Overruns: Discovering A Power-Law Distribution","authors":"B. Flyvbjerg, Alexander Budzier, Jong Seok Lee, M. Keil, Daniel Lunn, Dirk W. Bester","doi":"10.1080/07421222.2022.2096544","DOIUrl":null,"url":null,"abstract":"ABSTRACT If managers assume a normal or near-normal distribution of Information Technology (IT) project cost overruns, as is common, and cost overruns can be shown to follow a power-law distribution, managers may be unwittingly exposing their organizations to extreme risk by severely underestimating the probability of large cost overruns. In this research, we collect and analyze a large sample comprised of 5,392 IT projects to empirically examine the probability distribution of IT project cost overruns. Further, we propose and examine a mechanism that can explain such a distribution. Our results reveal that IT projects are far riskier in terms of cost than normally assumed by decision makers and scholars. Specifically, we found that IT project cost overruns follow a power-law distribution in which there are a large number of projects with relatively small overruns and a fat tail that includes a smaller number of projects with extreme overruns. A possible generative mechanism for the identified power-law distribution is found in interdependencies among technological components in IT systems. We propose and demonstrate, through computer simulation, that a problem in a single technological component can lead to chain reactions in which other interdependent components are affected, causing substantial overruns. What the power law tells us is that extreme IT project cost overruns will occur and that the prevalence of these will be grossly underestimated if managers assume that overruns follow a normal or near-normal distribution. This underscores the importance of realistically assessing and mitigating the cost risk of new IT projects up front.","PeriodicalId":50154,"journal":{"name":"Journal of Management Information Systems","volume":"39 1","pages":"607 - 639"},"PeriodicalIF":5.9000,"publicationDate":"2022-07-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Management Information Systems","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1080/07421222.2022.2096544","RegionNum":2,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"COMPUTER SCIENCE, INFORMATION SYSTEMS","Score":null,"Total":0}
引用次数: 7

Abstract

ABSTRACT If managers assume a normal or near-normal distribution of Information Technology (IT) project cost overruns, as is common, and cost overruns can be shown to follow a power-law distribution, managers may be unwittingly exposing their organizations to extreme risk by severely underestimating the probability of large cost overruns. In this research, we collect and analyze a large sample comprised of 5,392 IT projects to empirically examine the probability distribution of IT project cost overruns. Further, we propose and examine a mechanism that can explain such a distribution. Our results reveal that IT projects are far riskier in terms of cost than normally assumed by decision makers and scholars. Specifically, we found that IT project cost overruns follow a power-law distribution in which there are a large number of projects with relatively small overruns and a fat tail that includes a smaller number of projects with extreme overruns. A possible generative mechanism for the identified power-law distribution is found in interdependencies among technological components in IT systems. We propose and demonstrate, through computer simulation, that a problem in a single technological component can lead to chain reactions in which other interdependent components are affected, causing substantial overruns. What the power law tells us is that extreme IT project cost overruns will occur and that the prevalence of these will be grossly underestimated if managers assume that overruns follow a normal or near-normal distribution. This underscores the importance of realistically assessing and mitigating the cost risk of new IT projects up front.
IT项目成本超支的经验现实:幂律分布的发现
如果管理人员假设信息技术(IT)项目成本超支的正态分布或接近正态分布是常见的,并且成本超支可以显示为遵循幂律分布,那么管理人员可能会因严重低估大规模成本超支的概率而在不知不觉中使其组织暴露于极端风险之中。在本研究中,我们收集并分析了由5392个IT项目组成的大样本,以经验性地检查IT项目成本超支的概率分布。此外,我们提出并检验了一种可以解释这种分布的机制。我们的研究结果表明,IT项目在成本方面比决策者和学者通常认为的风险要大得多。具体地说,我们发现IT项目成本超支遵循幂律分布,其中有大量的项目具有相对较小的超支,并且有一个胖尾,其中包括少数具有极端超支的项目。在IT系统中技术组件之间的相互依赖关系中发现了确定的幂律分布的可能生成机制。我们通过计算机模拟提出并证明,单个技术组件中的问题可能导致连锁反应,其中其他相互依赖的组件受到影响,导致大量超支。幂律告诉我们的是,极端的IT项目成本超支将会发生,如果管理人员假设超支遵循正态或接近正态分布,那么这种情况的普遍程度将被严重低估。这强调了预先实际评估和降低新IT项目成本风险的重要性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Journal of Management Information Systems
Journal of Management Information Systems 工程技术-计算机:信息系统
CiteScore
10.20
自引率
13.00%
发文量
34
审稿时长
6 months
期刊介绍: Journal of Management Information Systems is a widely recognized forum for the presentation of research that advances the practice and understanding of organizational information systems. It serves those investigating new modes of information delivery and the changing landscape of information policy making, as well as practitioners and executives managing the information resource.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信