The Reconfiguration of Network at 20 kV Distribution System Nagan Raya Substation with the Addition of the Krueng Isep Hydroelectric Power Plant

Ediwan Ediwan, M. Muliadi, Mahalla Mahalla, N. Nazaruddin, Andi Mulkan
{"title":"The Reconfiguration of Network at 20 kV Distribution System Nagan Raya Substation with the Addition of the Krueng Isep Hydroelectric Power Plant","authors":"Ediwan Ediwan, M. Muliadi, Mahalla Mahalla, N. Nazaruddin, Andi Mulkan","doi":"10.25077/JNTE.V10N2.888.2021","DOIUrl":null,"url":null,"abstract":"Switching substations are usually supplied from one express feeder which can cause a low level of reliability due to disruption or outage on the express feeder. Also, the lack of power supply at the ends of the network causes voltage drops. One way to solve this problem is to reconfigure the network. In this study, testing was carried out on a distribution system in the Nagan Raya Regency, namely the distribution system of PT. PLN (Persero) ULP Jeuram originally had a radial system. Furthermore, the distribution system was reconfigured with the Krueng Isep hydroelectric power plant which was included in the PLN ULP Jeuram grid so that the system that was originally radial became a loop configuration. The method used in analyzing the network reconfiguration process is to use the ETAP 12.6 application. As a result, after reconfiguring the network the voltage increased from 19.2 kV to 20.7 kV, the highest increase was at the Beutong Substation which reached 1.5 kV and decreased power losses in the network with a total of 188.2 kW and 263.1 kVAR. Furthermore, before the network reconfiguration, ULP Jeuram SAIFI value was 22.25 times/customers and SAIDI values 1337.74 minutes/ customers. However, after reconfiguring the network, ULP Jeuram SAIFI value fell to 15.39 times/customers and SAIDI to 945.6 minutes/customers, resulting in an increase in system reliability by 70.69%. Keyword: Reconfiguration of network, distribution system, hydroelectric power plant, SAIDI, SAIFI","PeriodicalId":30660,"journal":{"name":"Jurnal Nasional Teknik Elektro","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Nasional Teknik Elektro","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.25077/JNTE.V10N2.888.2021","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

Abstract

Switching substations are usually supplied from one express feeder which can cause a low level of reliability due to disruption or outage on the express feeder. Also, the lack of power supply at the ends of the network causes voltage drops. One way to solve this problem is to reconfigure the network. In this study, testing was carried out on a distribution system in the Nagan Raya Regency, namely the distribution system of PT. PLN (Persero) ULP Jeuram originally had a radial system. Furthermore, the distribution system was reconfigured with the Krueng Isep hydroelectric power plant which was included in the PLN ULP Jeuram grid so that the system that was originally radial became a loop configuration. The method used in analyzing the network reconfiguration process is to use the ETAP 12.6 application. As a result, after reconfiguring the network the voltage increased from 19.2 kV to 20.7 kV, the highest increase was at the Beutong Substation which reached 1.5 kV and decreased power losses in the network with a total of 188.2 kW and 263.1 kVAR. Furthermore, before the network reconfiguration, ULP Jeuram SAIFI value was 22.25 times/customers and SAIDI values 1337.74 minutes/ customers. However, after reconfiguring the network, ULP Jeuram SAIFI value fell to 15.39 times/customers and SAIDI to 945.6 minutes/customers, resulting in an increase in system reliability by 70.69%. Keyword: Reconfiguration of network, distribution system, hydroelectric power plant, SAIDI, SAIFI
20kv配电系统Nagan Raya变电站与Krueng Isep水电站并网改造
交换变电站通常由一个快速馈线供电,由于快速馈线的中断或停电,可能导致可靠性低。此外,在网络的两端缺乏电力供应会导致电压下降。解决这个问题的一种方法是重新配置网络。在本研究中,对Nagan Raya reggency的配电系统进行了测试,即PT. PLN (Persero) ULP Jeuram的配电系统最初采用径向系统。此外,配电系统重新配置了Krueng Isep水力发电厂,该发电厂被纳入PLN ULP Jeuram电网,因此最初的径向系统变成了环路配置。分析网络重构过程的方法是使用ETAP 12.6应用程序。改造后的电网电压由19.2 kV提高到20.7 kV,其中北通变电站的电压增幅最大,达到1.5 kV,降低了电网的功率损耗,共计188.2 kW和263.1 kVAR。此外,网络重构前,ULP Jeuram的SAIFI值为22.25次/客户,SAIDI值为1337.74分钟/客户。但在重新配置网络后,ULP Jeuram的SAIFI值降至15.39次/客户,SAIDI降至945.6分钟/客户,系统可靠性提高了70.69%。关键词:电网重构,配电系统,水电站,SAIDI, SAIFI
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
20
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信