{"title":"Design Delays in Building Projects in India: Effects and Remedies","authors":"D. Das, F. Emuze","doi":"10.5130/AJCEB.V21I1.7453","DOIUrl":null,"url":null,"abstract":"Empirical evidence shows that design-related challenges influence delay in building projects in India. Based on case studies of building projects from the capital region of Odisha Province of India, the factors relating to consultants and design have been identified and policy interventions were compiled to reduce design linked delay. A survey method to collect data, statistical analysis and a Systems Dynamics modelling approach were used according to different scenarios to propose strategic interventions. The findings suggested that complexity of design and compilation of documents, and the combined complexity of both can cause substantial delay. The model results revealed that the combined effect of appointing competent consultants and communicating effectively could reduce delay significantly. The novelty of the study lies in using a systems approach to develop causal feedback relationships among variables, as opposed to considering one origin of the problem at a time. The study makes three contributions: (1) design-linked challenges and mechanisms of delay, based on causal feedback relationships in building construction, can be diagnosed to evolve appropriate remedial measures; (2) impacts of different interventions can be visualised quantitatively under different scenarios; and (3) an alternative methodology to examine the trend of the project period is offered.","PeriodicalId":51729,"journal":{"name":"Construction Economics and Building","volume":null,"pages":null},"PeriodicalIF":1.8000,"publicationDate":"2021-02-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction Economics and Building","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5130/AJCEB.V21I1.7453","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 1
Abstract
Empirical evidence shows that design-related challenges influence delay in building projects in India. Based on case studies of building projects from the capital region of Odisha Province of India, the factors relating to consultants and design have been identified and policy interventions were compiled to reduce design linked delay. A survey method to collect data, statistical analysis and a Systems Dynamics modelling approach were used according to different scenarios to propose strategic interventions. The findings suggested that complexity of design and compilation of documents, and the combined complexity of both can cause substantial delay. The model results revealed that the combined effect of appointing competent consultants and communicating effectively could reduce delay significantly. The novelty of the study lies in using a systems approach to develop causal feedback relationships among variables, as opposed to considering one origin of the problem at a time. The study makes three contributions: (1) design-linked challenges and mechanisms of delay, based on causal feedback relationships in building construction, can be diagnosed to evolve appropriate remedial measures; (2) impacts of different interventions can be visualised quantitatively under different scenarios; and (3) an alternative methodology to examine the trend of the project period is offered.
期刊介绍:
Construction Economics and Building (formerly known as the Australasian Journal of Construction Economics and Building [AJCEB]) is a peer reviewed, open access publication for original research into all aspects of the economics and management of building and construction, quantity surveying and property management as well as construction and property education. It is free for authors, readers and libraries.