ANALISIS KELAYAKAN INVESTASI PEMBANGUNAN READY MIX PLANT (STUDI KASUS PT. X DI JAWA TIMUR)

Prokons Pub Date : 2019-07-18 DOI:10.33795/prokons.v12i2.165
Wilda Itatul Izza, Susapto, Fadjar Purnomo
{"title":"ANALISIS KELAYAKAN INVESTASI PEMBANGUNAN READY MIX PLANT (STUDI KASUS PT. X DI JAWA TIMUR)","authors":"Wilda Itatul Izza, Susapto, Fadjar Purnomo","doi":"10.33795/prokons.v12i2.165","DOIUrl":null,"url":null,"abstract":"PT. X will built a 3,000-m2 ready mix plant able to demand of X-Y highway contruction project. The built was planned in 3 alternative site: in Gempol—72.6km from the project site, in Purwosari—44.6km from project site, and in Singosari—53km from project site . The purpose of this study is: 1) to determine investment feasibility by technical aspect of each alternative site; 2) to determine investment feasibility by financial aspect based on feasibility parameters; 3) to determine the level of sensitivity of financial feasibilty by seeing the increase of materials and operational costs, the decrease of selling price and product demand.Technical feasibility was analyzed based on the result of questionnaires by calculating the percentage of each variable such as materials; man power; equipment; transportation; provision of water, electricity, and telephone line; and circumstances of social, environtment, community. The percantage of variable was of influential factor to choose the site by ranking method. Financial feasibility resulted from the cost of each site was analyzed based on feasibility parameter of Net Present Value (NPV), Benefit Cost Ratio (BCR), Internal Rate of Return (IRR), and Payback Period (PP). The last analysis was the sensitivity one to determine the level of sensitivity by seeing the increase of materials and operational costs, the decrease of selling price and product demand.The result of investment feasibility by technical aspect is feasible in Purwosari, Pasuruan District with a close range of raw materials; adequate availability of man power; adequate equipment; adequate transportation facilities; provision of water, electricity, and telephone lines; supporting from social, environtment, and community. The investment feasibility is financially feasible at NPV = IDR7,075,213,700; BCR = 1.047; IRR = 64.875%, and PP = 1,13 year. The result of sensitivity analysis shows that the PT. X is still able to adjust the 1%-8% tollerable increasing materials cost, 1%-7% increasing operational cost, 1%-6% decreasing selling price, and 1%-6% decreasing product demand. Keywords: BCR, feasibility, investment, IRR, NPV, PP, ready mix plant, sensitivity.","PeriodicalId":34836,"journal":{"name":"Prokons","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-07-18","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Prokons","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.33795/prokons.v12i2.165","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

PT. X will built a 3,000-m2 ready mix plant able to demand of X-Y highway contruction project. The built was planned in 3 alternative site: in Gempol—72.6km from the project site, in Purwosari—44.6km from project site, and in Singosari—53km from project site . The purpose of this study is: 1) to determine investment feasibility by technical aspect of each alternative site; 2) to determine investment feasibility by financial aspect based on feasibility parameters; 3) to determine the level of sensitivity of financial feasibilty by seeing the increase of materials and operational costs, the decrease of selling price and product demand.Technical feasibility was analyzed based on the result of questionnaires by calculating the percentage of each variable such as materials; man power; equipment; transportation; provision of water, electricity, and telephone line; and circumstances of social, environtment, community. The percantage of variable was of influential factor to choose the site by ranking method. Financial feasibility resulted from the cost of each site was analyzed based on feasibility parameter of Net Present Value (NPV), Benefit Cost Ratio (BCR), Internal Rate of Return (IRR), and Payback Period (PP). The last analysis was the sensitivity one to determine the level of sensitivity by seeing the increase of materials and operational costs, the decrease of selling price and product demand.The result of investment feasibility by technical aspect is feasible in Purwosari, Pasuruan District with a close range of raw materials; adequate availability of man power; adequate equipment; adequate transportation facilities; provision of water, electricity, and telephone lines; supporting from social, environtment, and community. The investment feasibility is financially feasible at NPV = IDR7,075,213,700; BCR = 1.047; IRR = 64.875%, and PP = 1,13 year. The result of sensitivity analysis shows that the PT. X is still able to adjust the 1%-8% tollerable increasing materials cost, 1%-7% increasing operational cost, 1%-6% decreasing selling price, and 1%-6% decreasing product demand. Keywords: BCR, feasibility, investment, IRR, NPV, PP, ready mix plant, sensitivity.
预拌厂建设投资分析
X公司将根据X- y高速公路建设项目的需要,建设一座3000平方米的预拌料厂。该建筑规划在3个备选地点:gempol -距离项目地点72.6公里,purwosari -距离项目地点44.6公里,singosari -距离项目地点53公里。本研究的目的是:1)从技术角度确定每个备选场址的投资可行性;2)根据可行性参数,从财务方面确定投资可行性;3)通过观察材料和运营成本的增加、销售价格的下降和产品需求的下降来确定财务可行性的敏感性。根据问卷调查结果,计算材料等各变量的百分比,分析技术可行性;男人的权力;设备;交通运输;提供水、电和电话线;以及社会,环境,社区的环境。变量的百分比是排序法选择站点的影响因素。根据净现值(NPV)、效益成本比(BCR)、内部收益率(IRR)和投资回收期(PP)等可行性参数,分析各选址成本产生的财务可行性。最后一个分析是灵敏度,通过观察材料和运营成本的增加,销售价格的下降和产品需求来确定灵敏度的水平。从技术角度进行投资可行性分析的结果,在原料来源较近的帕苏鲁区普沃萨里是可行的;人力资源充足;足够的设备;充足的交通设施;提供水、电和电话线;来自社会、环境和社区的支持。投资可行性在财政上是可行的,NPV = 7,075,213,700印尼盾;BCR = 1.047;IRR = 64.875%, PP = 1,13年。敏感性分析结果表明,PT. X仍能调整材料成本可承受的1%-8%的增长,运营成本可承受的1%-7%的增长,销售价格可承受的1%-6%的下降,产品需求可承受的1%-6%的下降。关键词:BCR,可行性,投资,IRR, NPV, PP,预拌装置,敏感性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
6
审稿时长
8 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信