Trenchless construction of Phase IIIA district cooling system (DCS) by TBM pipejacking and hand-dug tunnelling on Kai Tak Development: part I – design and construction considerations

Q2 Engineering
Wilson W S Mok, Victor K Lo, Germaine T M Chau, Louis Y M Lau
{"title":"Trenchless construction of Phase IIIA district cooling system (DCS) by TBM pipejacking and hand-dug tunnelling on Kai Tak Development: part I – design and construction considerations","authors":"Wilson W S Mok, Victor K Lo, Germaine T M Chau, Louis Y M Lau","doi":"10.1080/1023697X.2017.1413958","DOIUrl":null,"url":null,"abstract":"ABSTRACT In this paper, the design and construction of 1.75 km of 1200 mm, 1500 mm and 2800 mm diameter concrete sleeve pipelines, using slurry operated tunnel boring machines (TBM), for installation of district cooling system (DCS) pipelines, in highly variable ground conditions in the Kowloon Bay area are discussed. This was the first time that TBM pipejacking has been used in Hong Kong to construct pipelines below the seabed. The construction techniques for working pits to suit site constraints are also discussed. Hand-dug tunnels, constructed with hand-mining shield and horizontal pipe-piles, for DCS pipeline installation, due to the constraints by utilities and interfacing contracts, are highlighted.","PeriodicalId":35587,"journal":{"name":"Transactions Hong Kong Institution of Engineers","volume":"25 1","pages":"56 - 66"},"PeriodicalIF":0.0000,"publicationDate":"2018-01-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1080/1023697X.2017.1413958","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Transactions Hong Kong Institution of Engineers","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1080/1023697X.2017.1413958","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q2","JCRName":"Engineering","Score":null,"Total":0}
引用次数: 1

Abstract

ABSTRACT In this paper, the design and construction of 1.75 km of 1200 mm, 1500 mm and 2800 mm diameter concrete sleeve pipelines, using slurry operated tunnel boring machines (TBM), for installation of district cooling system (DCS) pipelines, in highly variable ground conditions in the Kowloon Bay area are discussed. This was the first time that TBM pipejacking has been used in Hong Kong to construct pipelines below the seabed. The construction techniques for working pits to suit site constraints are also discussed. Hand-dug tunnels, constructed with hand-mining shield and horizontal pipe-piles, for DCS pipeline installation, due to the constraints by utilities and interfacing contracts, are highlighted.
启德发展计划第三期第二期区域供冷系统(DCS)的隧道掘进机顶管及手挖隧道非开挖施工:第一部分-设计及施工考虑
摘要:本文讨论了在九龙湾地区高度多变的地面条件下,为安装区域供冷系统(DCS)管道,采用浆式隧道掘进机(TBM)设计和施工1.75 km直径为1200mm、1500mm和2800 mm的混凝土套管管道。这是香港首次采用隧道掘进机截管在海床下建造管道。讨论了适应现场条件的工坑施工技术。重点介绍了由于公用事业和接口合同的限制,用于DCS管道安装的手挖隧道,采用手挖盾和水平管桩施工。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Transactions Hong Kong Institution of Engineers
Transactions Hong Kong Institution of Engineers Engineering-Engineering (all)
CiteScore
2.70
自引率
0.00%
发文量
22
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信