{"title":"Borssele V slip joint connection: design, certification and installation of the world's first full‐size submerged slip joint","authors":"Sander Suur, Ferdy Hengeveld","doi":"10.1002/stco.202100038","DOIUrl":null,"url":null,"abstract":"In April 2020 the world's first full‐size submerged slip joint connection was installed at the Borssele Site V offshore wind farm. This event marked the launch of a new, alternative transition piece/monopile (TP/MP) connection for the offshore wind market. An extensive qualification programme in terms of numerical modelling and testing was set up prior to installing the slip joint. This process was witnessed, reviewed and accepted by DNVGL. It led to a certified slip joint design for Borssele V, with a 9.5 MW wind turbine generator (WTG) on top of the foundation as well as an A‐level component certificate for the slip joint in general. The installation of the slip joint for Borssele V was the first use of this connection in a commercial full‐size wind turbine.","PeriodicalId":54183,"journal":{"name":"Steel Construction-Design and Research","volume":null,"pages":null},"PeriodicalIF":1.2000,"publicationDate":"2022-04-11","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Steel Construction-Design and Research","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1002/stco.202100038","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"CONSTRUCTION & BUILDING TECHNOLOGY","Score":null,"Total":0}
引用次数: 0
Abstract
In April 2020 the world's first full‐size submerged slip joint connection was installed at the Borssele Site V offshore wind farm. This event marked the launch of a new, alternative transition piece/monopile (TP/MP) connection for the offshore wind market. An extensive qualification programme in terms of numerical modelling and testing was set up prior to installing the slip joint. This process was witnessed, reviewed and accepted by DNVGL. It led to a certified slip joint design for Borssele V, with a 9.5 MW wind turbine generator (WTG) on top of the foundation as well as an A‐level component certificate for the slip joint in general. The installation of the slip joint for Borssele V was the first use of this connection in a commercial full‐size wind turbine.
2020年4月,世界上第一个全尺寸水下滑动接头在Borssele Site V海上风电场安装。此次活动标志着海上风电市场新的替代过渡件/单桩(TP/MP)连接的推出。在安装滑动接头之前,建立了一个广泛的数值建模和测试鉴定计划。DNVGL见证、审查并接受了该过程。它为Borssele V设计了一个经过认证的滑动接头,在基础顶部安装了一台9.5兆瓦的风力发电机,并为滑动接头提供了a级组件证书。Borssele V滑动接头的安装是这种连接首次在商用全尺寸风力涡轮机中使用。
期刊介绍:
Steel Construction publishes peerreviewed papers covering the entire field of steel construction research. In the interests of "construction without depletion", it skilfully combines steel with other forms of construction employing concrete, glass, cables and membranes to form integrated steelwork systems. Since 2010 Steel Construction is the official journal for ECCS- European Convention for Constructional Steelwork members. You will find more information about membership on the ECCS homepage. Topics include: -Design and construction of structures -Methods of analysis and calculation -Experimental and theoretical research projects and results -Composite construction -Steel buildings and bridges -Cable and membrane structures -Structural glazing -Masts and towers -Vessels, cranes and hydraulic engineering structures -Fire protection -Lightweight structures