{"title":"Resettlement delays in the Dasu Hydropower Project: assessing impacts on the affected people and communities","authors":"Shafiq Ahmad, Guoqing Shi, M. Zaman","doi":"10.1080/07900627.2022.2128078","DOIUrl":null,"url":null,"abstract":"ABSTRACT This case study of the Dasu Hydropower Project in Pakistan investigates the impacts of delays in resettlement on project-affected people. The analyses presented here suggest that delays in the implementation of resettlement plans lead to additional socio-economic, environmental and psychological impacts on local communities. In addition, temporary resettlement of some households prior to relocation and resettlement at the planned sites aggravated these impacts, further complicating planned resettlement. The authors argue in favour of resettlement ahead of any civil works to reduce negative project impacts.","PeriodicalId":50279,"journal":{"name":"International Journal of Water Resources Development","volume":"39 1","pages":"663 - 680"},"PeriodicalIF":2.0000,"publicationDate":"2022-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Water Resources Development","FirstCategoryId":"93","ListUrlMain":"https://doi.org/10.1080/07900627.2022.2128078","RegionNum":3,"RegionCategory":"环境科学与生态学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"WATER RESOURCES","Score":null,"Total":0}
引用次数: 2

Abstract

ABSTRACT This case study of the Dasu Hydropower Project in Pakistan investigates the impacts of delays in resettlement on project-affected people. The analyses presented here suggest that delays in the implementation of resettlement plans lead to additional socio-economic, environmental and psychological impacts on local communities. In addition, temporary resettlement of some households prior to relocation and resettlement at the planned sites aggravated these impacts, further complicating planned resettlement. The authors argue in favour of resettlement ahead of any civil works to reduce negative project impacts.
达苏水电项目移民安置延误:评估对受影响人群和社区的影响
本研究以巴基斯坦达苏水电项目为例,探讨了延期安置对项目受影响人群的影响。这里提出的分析表明,延迟执行重新安置计划会对当地社区造成额外的社会经济、环境和心理影响。此外,在重新安置和在计划地点重新安置之前临时安置一些家庭加剧了这些影响,使计划的重新安置进一步复杂化。作者主张在任何土建工程之前进行重新安置,以减少项目的负面影响。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
8.10
自引率
9.70%
发文量
23
审稿时长
1 months
期刊介绍: International Journal of Water Resources Development is a policy and practice-oriented Journal that covers all aspects of water resources policy, management, development and governance. It is an interdisciplinary journal that focuses on water resources and their economic, financial, social and environmental-related impacts. Contributions which include the interdependences and inter-linkages between the water and the agricultural, energy, industrial and health sectors in both developed and developing countries, both at present and in the future, are welcome.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信