EVALUATION OF THE PROCUREMENT MANAGEMENT SYSTEM FOR RESIDENTIAL COMPLEX PROJECTS IN ERBIL GOVERNORATE

A. Mohammed
{"title":"EVALUATION OF THE PROCUREMENT MANAGEMENT SYSTEM FOR RESIDENTIAL COMPLEX PROJECTS IN ERBIL GOVERNORATE","authors":"A. Mohammed","doi":"10.31272/jeasd.27.1.5","DOIUrl":null,"url":null,"abstract":"This study aims to evaluate the procurement management system of residential complex projects in Erbil Governorate by adopting a case study for (20) constructed projects during 2007-2019, to calculate the percentage of procurement management practice and the risks that have a significant impact on cost, time, and quality. Based on a literature review and discussion with experienced construction managers and procurement officers, a questionnaire has been designed which represents a successful plan for a procurement management system that consists of ten phases, each of five items, and the risk results associated with the improper practice. The questionnaire was delivered to stakeholders working on residential complex projects to calculate the average practice of procurement management. It is revealed that 70% of residential complex projects practiced procurement management process with a percentage below 50%. Which is considered below the acceptable rate. The average practice of procurement management phases ranges between 33% for procurement risk management and 58.5% for forecasting.  The study reviled that the practice of procurement management affects the cost and time mostly. There are 26 risks that range between high and significant categories for cost and 22 risks range between high and significant categories for time. The most significant factors for procurement management are creating an appropriate risk response plan, integrating the procurement plan with the budgeting, scheduling procurement due to dates and quantities, using the tendering procedure, and procurement quality assurance. This study may contribute to solving problems for future projects by improving the current system.","PeriodicalId":33282,"journal":{"name":"Journal of Engineering and Sustainable Development","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Engineering and Sustainable Development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.31272/jeasd.27.1.5","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This study aims to evaluate the procurement management system of residential complex projects in Erbil Governorate by adopting a case study for (20) constructed projects during 2007-2019, to calculate the percentage of procurement management practice and the risks that have a significant impact on cost, time, and quality. Based on a literature review and discussion with experienced construction managers and procurement officers, a questionnaire has been designed which represents a successful plan for a procurement management system that consists of ten phases, each of five items, and the risk results associated with the improper practice. The questionnaire was delivered to stakeholders working on residential complex projects to calculate the average practice of procurement management. It is revealed that 70% of residential complex projects practiced procurement management process with a percentage below 50%. Which is considered below the acceptable rate. The average practice of procurement management phases ranges between 33% for procurement risk management and 58.5% for forecasting.  The study reviled that the practice of procurement management affects the cost and time mostly. There are 26 risks that range between high and significant categories for cost and 22 risks range between high and significant categories for time. The most significant factors for procurement management are creating an appropriate risk response plan, integrating the procurement plan with the budgeting, scheduling procurement due to dates and quantities, using the tendering procedure, and procurement quality assurance. This study may contribute to solving problems for future projects by improving the current system.
埃尔比勒省住宅综合体项目采购管理体系评价
本研究旨在通过对2007-2019年期间(20)个已建项目的案例研究,评估埃尔比勒省住宅综合体项目的采购管理系统,以计算采购管理实践的百分比以及对成本、时间和质量有重大影响的风险。在文献回顾和与经验丰富的施工经理和采购官员讨论的基础上,设计了一份问卷,该问卷代表了采购管理系统的成功计划,该系统由十个阶段组成,每个阶段包括五个项目,以及与不当做法相关的风险结果。问卷已分发给住宅综合体项目的利益相关者,以计算采购管理的平均做法。据统计,70%的住宅综合体项目实施了采购管理流程,这一比例低于50%。这被认为低于可接受的比率。采购管理阶段的平均做法在采购风险管理方面为33%,在预测方面为58.5%。研究表明,采购管理实践对成本和时间的影响最大。有26种风险在成本的高和重要类别之间,22种风险在时间的高和重大类别之间。采购管理的最重要因素是制定适当的风险应对计划,将采购计划与预算编制相结合,根据日期和数量安排采购,使用招标程序,以及采购质量保证。这项研究可能有助于通过改进现有系统来解决未来项目的问题。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
0.70
自引率
0.00%
发文量
74
审稿时长
50 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信