Modified Resource-Constrained Project Scheduling to Minimize Idle Time for Banbury Mixing Process: A Case Study in the Tire Manufacturing Industry

IF 1.4 Q4 ENGINEERING, INDUSTRIAL
A. Butrat, S. Supsomboon
{"title":"Modified Resource-Constrained Project Scheduling to Minimize Idle Time for Banbury Mixing Process: A Case Study in the Tire Manufacturing Industry","authors":"A. Butrat, S. Supsomboon","doi":"10.2478/mspe-2023-0029","DOIUrl":null,"url":null,"abstract":"Abstract The Banbury mixing process (BMP) is to supplies the specific characteristic compounds for the tire manufacturing process. Idle time in the BMP was a problem caused by the aging process between mixing steps and the limited space for processing, measured in pallets. In this study, the resource-constrained project scheduling model (RCPS) is modified in case of the objective function and the input value of resource constraint to minimize idle time (SST). The complete minimization (Cmax) is changed from minimizing the starting time of the last job to the starting time of all jobs. In addition, the non-limited resource is defined as the input for the space capacity to reduce the idle time. As the results, the SST can provide the schedule that make less 5 time periods of idle time. Moreover, when considering the relationship between mixing and aging, aging process that is scheduled from SST starts immediately comparison to Cmax that some of aging process are not. Furthermore, the effect of the quantity of pallets was also examined. Although the non-limited resource does not make any delay to the schedule but the limited quantity is not. When pallets are limited, aging jobs were significantly impacted, with the last aging pallet being delayed. To reduce delays, it prepares an adequate supply of pallets that is close to or equal to its requirement that is defined by the non-limited resource. Further research combining the scheduling of the BMP with the tire manufacturing process and more techniques to modify RCPS are applied.","PeriodicalId":44097,"journal":{"name":"Management Systems in Production Engineering","volume":null,"pages":null},"PeriodicalIF":1.4000,"publicationDate":"2023-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Management Systems in Production Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2478/mspe-2023-0029","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 0

Abstract

Abstract The Banbury mixing process (BMP) is to supplies the specific characteristic compounds for the tire manufacturing process. Idle time in the BMP was a problem caused by the aging process between mixing steps and the limited space for processing, measured in pallets. In this study, the resource-constrained project scheduling model (RCPS) is modified in case of the objective function and the input value of resource constraint to minimize idle time (SST). The complete minimization (Cmax) is changed from minimizing the starting time of the last job to the starting time of all jobs. In addition, the non-limited resource is defined as the input for the space capacity to reduce the idle time. As the results, the SST can provide the schedule that make less 5 time periods of idle time. Moreover, when considering the relationship between mixing and aging, aging process that is scheduled from SST starts immediately comparison to Cmax that some of aging process are not. Furthermore, the effect of the quantity of pallets was also examined. Although the non-limited resource does not make any delay to the schedule but the limited quantity is not. When pallets are limited, aging jobs were significantly impacted, with the last aging pallet being delayed. To reduce delays, it prepares an adequate supply of pallets that is close to or equal to its requirement that is defined by the non-limited resource. Further research combining the scheduling of the BMP with the tire manufacturing process and more techniques to modify RCPS are applied.
改进资源约束项目调度以减少班伯里混合过程的空闲时间:轮胎制造业的案例研究
班伯里混合工艺(BMP)是为轮胎制造过程提供特定的特征化合物。BMP中的空闲时间是由混合步骤之间的老化过程和托盘中测量的有限处理空间引起的问题。在本研究中,在目标函数和资源约束的输入值的情况下,对资源约束的项目调度模型(RCPS)进行了修改,以最小化空闲时间(SST)。完全最小化(Cmax)从最小化最后一个作业的开始时间变为最小化所有作业的开始时刻。此外,非受限资源被定义为空间容量的输入,以减少空闲时间。因此,SST可以提供少于5个空闲时间段的时间表。此外,当考虑混合和老化之间的关系时,从SST计划的老化过程与一些老化过程没有的Cmax相比立即开始。此外,还考察了托盘数量的影响。尽管非有限资源不会对时间表造成任何延迟,但有限数量不会。当托盘受到限制时,老化作业会受到严重影响,最后一个老化托盘会延迟。为了减少延误,它准备了足够的托盘供应,这些托盘接近或等于由非有限资源定义的需求。将BMP的调度与轮胎制造过程相结合进行进一步的研究,并应用更多的技术来修改RCPS。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
4.30
自引率
13.30%
发文量
48
审稿时长
10 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信