ANALISIS PENGENDALIAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN EARNED VALUE CONCEPT (EVC) DAN CRITICAL PATH METHOD (CPM) (Studi Kasus : Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya)
{"title":"ANALISIS PENGENDALIAN WAKTU PROYEK KONTRUKSI MENGGUNAKAN EARNED VALUE CONCEPT (EVC) DAN CRITICAL PATH METHOD (CPM) (Studi Kasus : Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya)","authors":"Sehabul Milah","doi":"10.36423/JITSI.V1I1.478","DOIUrl":null,"url":null,"abstract":"Abstract— The success of a project is not separated from a series of covering activities the stages of planning, implementation and supervision. In time control of a project is indispensable for a project to be able to complete the project on time or earlier than planned. The method of time control used in this research is the method of Earned value concept and Critical Path method (CPM) .This Research was conducted on the advanced project of Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya District which aims to know the project performance and completion time of work on the construction project of the building. The data used in this study are Time Schedule, cost budget plan, and weekly progress financial statement. From analyst data, the result can be found that in the values of BCWP and BCWS after they are obtained by the SV, SPI, and predicting the project end time completion (ETS and EAS) and generating critical paths and float calculations. From the results of the analysis of the time of completion in Week 12 reporting advanced Project of Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya District experienced a delay of 3 weeks from 21 weeks to 24 weeks but the results of the delay CPM analysis occurred outside the critical path so there are still opportunities to complete the project on time or faster of the plan.Keywords — Earned value method (EVC), Critical Path Method (CPM), BCWP, BCWS, SV, SPI, ETS, EAS.Abstrak— Keberhasilan suatu proyek tidak lepas dari serangkaian aktivitas yang meliputi tahapan perencanaan, pelaksanaan dan pengawasan. Dalam Pengendalian waktu pada suatu proyek diperlukan agar suatu proyek mampu menyelesaikan proyek dengan tepat waktu atau lebih awal dari yang direncanakan. Metode pengendalian waktu yang digunakan pada penelitian ini adalah metode konsep nilai hasil (Earned Value Concept) dan Critical Path Method (CPM). Penelitian ini dilakukan pada Proyek Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya yang bertujuan untuk mengetahui kinerja proyek dan waktu penyelesaian pekerjaan pada proyek pembangunan gedung tersebut. Data-data yang digunakan dalam penelitian kali ini meliputi Time Schedule, Rencana Anggaran Biaya, dan laporan progress mingguan. Dari data tersebut dapat menghasilkan nilai BCWP dan BCWS setelah itu didapatkan nilai SV, SPI, serta memprediksi penyelesaian waktu akhir proyek (ETS dan EAS) dan menghasilkan jalur kritis dan perhitungan float. Dari hasil analisis terhadap waktu penyelesaian pada minggu ke 12 pelaporan Proyek Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya mengalami keterlambatan 3 minggu dari 21 minggu menjadi 24 minggu namun hasil analisis CPM keterlambatan yang terjadi diluar jalur kritis jadi masih ada kesempatan untuk menyelesaikan proyek tepat waktu atau lebih awal dari rencana.Kata kunci — Earned Value Method (EVC), Critical Path Method (CPM), BCWP, BCWS, SV, SPI, ETS, EAS.","PeriodicalId":32544,"journal":{"name":"Jurnal Ilmiah Teknik Sipil","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2020-10-14","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Ilmiah Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36423/JITSI.V1I1.478","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2
Abstract
Abstract— The success of a project is not separated from a series of covering activities the stages of planning, implementation and supervision. In time control of a project is indispensable for a project to be able to complete the project on time or earlier than planned. The method of time control used in this research is the method of Earned value concept and Critical Path method (CPM) .This Research was conducted on the advanced project of Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya District which aims to know the project performance and completion time of work on the construction project of the building. The data used in this study are Time Schedule, cost budget plan, and weekly progress financial statement. From analyst data, the result can be found that in the values of BCWP and BCWS after they are obtained by the SV, SPI, and predicting the project end time completion (ETS and EAS) and generating critical paths and float calculations. From the results of the analysis of the time of completion in Week 12 reporting advanced Project of Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya District experienced a delay of 3 weeks from 21 weeks to 24 weeks but the results of the delay CPM analysis occurred outside the critical path so there are still opportunities to complete the project on time or faster of the plan.Keywords — Earned value method (EVC), Critical Path Method (CPM), BCWP, BCWS, SV, SPI, ETS, EAS.Abstrak— Keberhasilan suatu proyek tidak lepas dari serangkaian aktivitas yang meliputi tahapan perencanaan, pelaksanaan dan pengawasan. Dalam Pengendalian waktu pada suatu proyek diperlukan agar suatu proyek mampu menyelesaikan proyek dengan tepat waktu atau lebih awal dari yang direncanakan. Metode pengendalian waktu yang digunakan pada penelitian ini adalah metode konsep nilai hasil (Earned Value Concept) dan Critical Path Method (CPM). Penelitian ini dilakukan pada Proyek Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya yang bertujuan untuk mengetahui kinerja proyek dan waktu penyelesaian pekerjaan pada proyek pembangunan gedung tersebut. Data-data yang digunakan dalam penelitian kali ini meliputi Time Schedule, Rencana Anggaran Biaya, dan laporan progress mingguan. Dari data tersebut dapat menghasilkan nilai BCWP dan BCWS setelah itu didapatkan nilai SV, SPI, serta memprediksi penyelesaian waktu akhir proyek (ETS dan EAS) dan menghasilkan jalur kritis dan perhitungan float. Dari hasil analisis terhadap waktu penyelesaian pada minggu ke 12 pelaporan Proyek Lanjutan Pembangunan Jalan Ruas Jalan Ciawi Singaparna Kabupaten Tasikmalaya mengalami keterlambatan 3 minggu dari 21 minggu menjadi 24 minggu namun hasil analisis CPM keterlambatan yang terjadi diluar jalur kritis jadi masih ada kesempatan untuk menyelesaikan proyek tepat waktu atau lebih awal dari rencana.Kata kunci — Earned Value Method (EVC), Critical Path Method (CPM), BCWP, BCWS, SV, SPI, ETS, EAS.
摘要“一个项目的成功离不开一系列的覆盖活动——规划、实施和监督阶段。项目的时间控制对于项目能够按时或早于计划完成项目是必不可少的。本研究采用的时间控制方法是挣值概念和关键路径法(CPM)。本研究是在塔西克马来亚县兰朱坦彭邦古南贾兰鲁亚西亚维县的高级项目上进行的,旨在了解该建筑施工项目的项目绩效和完工时间。本研究中使用的数据包括时间表、成本预算计划和每周进度财务报表。从分析数据中可以发现,在SV、SPI获得BCWP和BCWS值后,预测项目结束时间完成(ETS和EAS)并生成关键路径和浮点计算。根据第12周报告的Lanjutan Pembagunan Jalan Ruas Ciawi Singaparna Kabupaten Tasikmalaya区高级项目竣工时间分析结果,从21周到24周,延迟了3周,但CPM分析结果发生在关键路径之外,因此仍有机会按时或更快地完成项目计划。关键词“挣值法(EVC),关键路径法(CPM),BCWP,BCWS,SV,SPI,ETS,EAS。摘要€”项目的成功并不排除在包括规划、执行和监控级别的一系列活动之外。在项目的及时管理中,项目必须能够及时或早于计划完成项目。本研究中使用的时间控制方法是挣值概念和关键路径方法(CPM)概念方法。这项研究是对马来西亚开普省Singaparna Singaparna湖连续道路建设项目进行的,旨在了解该项目的绩效和建筑建设项目的完工时间。本研究中使用的数据包括时间表、预计成本时间表和每周进度报告。这些数据可以产生BCWP和BCWS值,然后获得SV、SPI值,并预测项目的结束时间(ETS和EAS),并产生临界线和浮点计算。根据对第12周解决时间的分析,Singaparna Kabupaten Tasikmalaya持续民用道路开发项目的报告延迟了3周,从21周延迟到24周,但CPM分析的延迟发生在关键线之外,因此仍有机会及时或早于计划完成项目。关键词“UNK]挣值法(EVC),关键路径法(CPM),BCWP,BCWS,SV,SPI,ETS,EAS。