Evaluating and classifying the impact of individual risk on the delayed EPC hydropower projects in the developing countries of Asia

Q3 Decision Sciences
S. Mai, Vatthanaly Siphada, Jianqiong Wang, Vinath Mekthanavanh, H. Hlaing, Pheng Sokliep
{"title":"Evaluating and classifying the impact of individual risk on the delayed EPC hydropower projects in the developing countries of Asia","authors":"S. Mai, Vatthanaly Siphada, Jianqiong Wang, Vinath Mekthanavanh, H. Hlaing, Pheng Sokliep","doi":"10.1504/IJRAM.2019.10022669","DOIUrl":null,"url":null,"abstract":"Many hydropower projects in the developing countries of Asia have currently adopted the project delivery method of engineering, procurement and construction (EPC). However, the EPC general contractors are facing many difficulties, resulting in schedule delays and considerable cost overrun. The purpose of this research is to evaluate the risks causing schedule delays of EPC hydropower projects in the developing countries of Asia. The study analysis and assessment of risks is based on survey questionnaires, which achieved the follow findings: (1) there are 21 main risks influencing on schedule delays; (2) scientifically rank the influence of every single risk on schedule delays; (3) provide a recommendation that could reduce or eliminate these risks on schedule delay of EPC hydropower projects. This study provides a valuable reference which helps investors and contractors finish on schedule to ensure the benefits when building EPC hydropower projects in the developing countries of Asia.","PeriodicalId":35420,"journal":{"name":"International Journal of Risk Assessment and Management","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-07-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Risk Assessment and Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/IJRAM.2019.10022669","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"Decision Sciences","Score":null,"Total":0}
引用次数: 1

Abstract

Many hydropower projects in the developing countries of Asia have currently adopted the project delivery method of engineering, procurement and construction (EPC). However, the EPC general contractors are facing many difficulties, resulting in schedule delays and considerable cost overrun. The purpose of this research is to evaluate the risks causing schedule delays of EPC hydropower projects in the developing countries of Asia. The study analysis and assessment of risks is based on survey questionnaires, which achieved the follow findings: (1) there are 21 main risks influencing on schedule delays; (2) scientifically rank the influence of every single risk on schedule delays; (3) provide a recommendation that could reduce or eliminate these risks on schedule delay of EPC hydropower projects. This study provides a valuable reference which helps investors and contractors finish on schedule to ensure the benefits when building EPC hydropower projects in the developing countries of Asia.
个体风险对亚洲发展中国家EPC水电项目延期影响的评估与分类
亚洲发展中国家的许多水电项目目前都采用了工程、采购和施工(EPC)的项目交付方式。然而,EPC总承包商面临着许多困难,导致进度延误和大量成本超支。本研究的目的是评估亚洲发展中国家EPC水电项目进度延误的风险。基于调查问卷对风险进行研究分析和评估,得出以下结论:(1)影响工期延误的主要风险有21种;(2) 科学地对每一种风险对进度延误的影响进行排序;(3) 提供一项建议,以减少或消除EPC水电项目进度延误的风险。本研究为投资者和承包商在亚洲发展中国家建设EPC水电项目提供了有价值的参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
International Journal of Risk Assessment and Management
International Journal of Risk Assessment and Management Decision Sciences-Statistics, Probability and Uncertainty
CiteScore
0.70
自引率
0.00%
发文量
1
期刊介绍: The IJRAM is an interdisciplinary and refereed journal that provides cross learning between: - Different business and economics, as well as scientific and technological, disciplines - Energy industries, environmental and ecological systems - Safety, public health and medical services - Software services, reliability and safety
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信