Achievement of first plasma and successful integrated commissioning in JT-60SA

IF 1.9 3区 工程技术 Q1 NUCLEAR SCIENCE & TECHNOLOGY
K. Takahashi , JT-60SA Integrated Project Team
{"title":"Achievement of first plasma and successful integrated commissioning in JT-60SA","authors":"K. Takahashi ,&nbsp;JT-60SA Integrated Project Team","doi":"10.1016/j.fusengdes.2025.115059","DOIUrl":null,"url":null,"abstract":"<div><div>Integrated Commissioning of JT-60SA, which will be the world’s largest tokamak until ITER operates, was completed in 2023. The device is designed to operate under good vacuum condition, which is by nature high insulation, and all superconducting magnets could withstand the operation voltage even if they were not Paschen proof. Applying the fast interlock system detecting vacuum deterioration inside the cryostat and the consideration of limited operation voltage (&lt;2kV) of PF magnets, the integrated commissioning of JT-60SA was restarted in May 2023. The pump-down of the cryostat and vacuum vessel and the cool-down of the magnets were subsequently carried out. Taking advantage of the experience of the first cool-down, its speed was enhanced by increasing helium flow. In addition, the vacuum vessel was baked at 200 °C for wall cleaning during cool-down to save time. Furthermore, glow discharge operation was also executed as another process of wall clearing. After the high voltage (HV) test of all magnets at the operation condition, which were high vacuum (∼10<sup>-6</sup> Pa) and cryogenic temperature (∼4K), the magnet energization was successfully carried out and followed by plasma operation. The first plasma with limiter configuration and plasma current of 130kA was obtained applying Trapped Particle Configuration (TPC) on Oct. 23, 2023. Electron Cyclotron Heating (ECH) assisted plasma breakdown was performed with a low toroidal electric field (∼0.15 V/m).</div></div>","PeriodicalId":55133,"journal":{"name":"Fusion Engineering and Design","volume":"216 ","pages":"Article 115059"},"PeriodicalIF":1.9000,"publicationDate":"2025-04-23","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Fusion Engineering and Design","FirstCategoryId":"5","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/S0920379625002571","RegionNum":3,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"NUCLEAR SCIENCE & TECHNOLOGY","Score":null,"Total":0}
引用次数: 0

Abstract

Integrated Commissioning of JT-60SA, which will be the world’s largest tokamak until ITER operates, was completed in 2023. The device is designed to operate under good vacuum condition, which is by nature high insulation, and all superconducting magnets could withstand the operation voltage even if they were not Paschen proof. Applying the fast interlock system detecting vacuum deterioration inside the cryostat and the consideration of limited operation voltage (<2kV) of PF magnets, the integrated commissioning of JT-60SA was restarted in May 2023. The pump-down of the cryostat and vacuum vessel and the cool-down of the magnets were subsequently carried out. Taking advantage of the experience of the first cool-down, its speed was enhanced by increasing helium flow. In addition, the vacuum vessel was baked at 200 °C for wall cleaning during cool-down to save time. Furthermore, glow discharge operation was also executed as another process of wall clearing. After the high voltage (HV) test of all magnets at the operation condition, which were high vacuum (∼10-6 Pa) and cryogenic temperature (∼4K), the magnet energization was successfully carried out and followed by plasma operation. The first plasma with limiter configuration and plasma current of 130kA was obtained applying Trapped Particle Configuration (TPC) on Oct. 23, 2023. Electron Cyclotron Heating (ECH) assisted plasma breakdown was performed with a low toroidal electric field (∼0.15 V/m).
JT-60SA实现首次等离子体和成功集成调试
JT-60SA的综合调试于2023年完成,在ITER运行之前,它将成为世界上最大的托卡马克。该装置设计在良好的真空条件下运行,这种条件本质上是高绝缘的,所有超导磁体即使不是Paschen proof也能承受工作电压。采用低温恒温器内部真空变质快速联锁检测系统,并考虑到PF磁体限定工作电压(2kV),于2023年5月重新启动JT-60SA综合调试。随后进行了低温恒温器和真空容器的泵降和磁体的冷却。利用第一次冷却的经验,通过增加氦气流量来提高速度。此外,真空容器在200°C下烘烤,以便在冷却时清洗壁面,以节省时间。此外,辉光放电操作还作为另一种清壁工艺进行。在高真空(~ 10-6 Pa)和低温(~ 4K)的工作条件下,对所有磁体进行高压(HV)测试后,磁体通电成功,随后进行等离子体操作。2023年10月23日,利用捕获粒子组态(TPC)获得了首个限制器组态等离子体,等离子体电流为130kA。在低环形电场(~ 0.15 V/m)下进行电子回旋加热(ECH)辅助等离子体击穿。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Fusion Engineering and Design
Fusion Engineering and Design 工程技术-核科学技术
CiteScore
3.50
自引率
23.50%
发文量
275
审稿时长
3.8 months
期刊介绍: The journal accepts papers about experiments (both plasma and technology), theory, models, methods, and designs in areas relating to technology, engineering, and applied science aspects of magnetic and inertial fusion energy. Specific areas of interest include: MFE and IFE design studies for experiments and reactors; fusion nuclear technologies and materials, including blankets and shields; analysis of reactor plasmas; plasma heating, fuelling, and vacuum systems; drivers, targets, and special technologies for IFE, controls and diagnostics; fuel cycle analysis and tritium reprocessing and handling; operations and remote maintenance of reactors; safety, decommissioning, and waste management; economic and environmental analysis of components and systems.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信