{"title":"Melo dam drilled steel pile wall: Restraining seepage through earth dam","authors":"Samuli Kiuru","doi":"10.1002/geot.202400070","DOIUrl":null,"url":null,"abstract":"<p>The Melo dam hydroelectric power plant in Nokia, Finland, was built between 1968 and 1971. The dam structure consists of a turbine hall on the right bank of the Kokemäenjoki river and a 120 m long earth dam adjacent to it. The earth dam was constructed with layers of moraine, gravel and rock fill. Over the years, seepage issues emerged, including a sinkhole in 2005, leading to temporary repairs. However, in 2019, a comprehensive renovation plan was initiated to develop a permanent solution. In 2022, KFS Finland carried out construction work to restrain seepage and ensure dam stability. This involved building a drilled steel pile wall along the entire length of the dam, using RD500 steel pipes drilled into the bedrock, reaching a depth of 67 m from the surface. The completed structure is now the deepest drilled pile wall in Finland, ensuring the dam's structural integrity for decades to come.</p>","PeriodicalId":39412,"journal":{"name":"Geomechanik und Tunnelbau","volume":"18 2","pages":"133-138"},"PeriodicalIF":0.0000,"publicationDate":"2025-02-17","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Geomechanik und Tunnelbau","FirstCategoryId":"1085","ListUrlMain":"https://onlinelibrary.wiley.com/doi/10.1002/geot.202400070","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"Earth and Planetary Sciences","Score":null,"Total":0}
引用次数: 0
Abstract
The Melo dam hydroelectric power plant in Nokia, Finland, was built between 1968 and 1971. The dam structure consists of a turbine hall on the right bank of the Kokemäenjoki river and a 120 m long earth dam adjacent to it. The earth dam was constructed with layers of moraine, gravel and rock fill. Over the years, seepage issues emerged, including a sinkhole in 2005, leading to temporary repairs. However, in 2019, a comprehensive renovation plan was initiated to develop a permanent solution. In 2022, KFS Finland carried out construction work to restrain seepage and ensure dam stability. This involved building a drilled steel pile wall along the entire length of the dam, using RD500 steel pipes drilled into the bedrock, reaching a depth of 67 m from the surface. The completed structure is now the deepest drilled pile wall in Finland, ensuring the dam's structural integrity for decades to come.
Geomechanik und TunnelbauEarth and Planetary Sciences-Geotechnical Engineering and Engineering Geology
CiteScore
1.20
自引率
0.00%
发文量
111
期刊介绍:
The contributions published in Geomechanics and Tunnelling deal with practical aspects of applied engineering geology, rock mechanics and rock engineering, soil mechanics and foundation engineering, and primarily tunnelling. Each issue focuses on a current topic or specific project. Brief news, reports from construction sites and news on conferences round off the content. From the start of 2009 Geomechanics and Tunnelling has been published as a bilingual English/German journal.