{"title":"Exact solution methods for the Resource Constrained Project Scheduling Problem with a flexible Project Structure","authors":"T. van der Beek, J.T. van Essen, J. Pruyn, K. Aardal","doi":"10.1016/j.ejor.2024.10.029","DOIUrl":null,"url":null,"abstract":"The Resource Constrained Project Scheduling Problem with a flexible Project Structure (RCPSP-PS) is a generalization of the Resource Constrained Project Scheduling Problem (RCPSP). In the RCPSP, the goal is to determine a minimal makespan schedule subject to precedence and resource constraints. The generalization introduced in the RCPSP-PS is that, instead of executing all activities, only a subset of all activities has to be executed. We present a model that is based on two graphs: one representing precedence relations and one representing the activity selection structure. The latter defines which subset of activities has to be executed. Additionally, we present theoretical properties of this model and give an exact solution method that makes use of these properties by generating cutting planes and setting bounds on variables. Furthermore, three problem properties are introduced to classify problems in the literature. We compare our model to a model from literature on instances that possess a subset of these three problem properties and find a reduction in computing time. Furthermore, by comparing results on instances that possess all problem properties, it is shown that the computing times are decreased and better lower bounds are found by the cutting planes and variable bounds presented in this paper.","PeriodicalId":55161,"journal":{"name":"European Journal of Operational Research","volume":"7 1","pages":""},"PeriodicalIF":6.0000,"publicationDate":"2024-11-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"European Journal of Operational Research","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1016/j.ejor.2024.10.029","RegionNum":2,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"OPERATIONS RESEARCH & MANAGEMENT SCIENCE","Score":null,"Total":0}
引用次数: 0
Abstract
The Resource Constrained Project Scheduling Problem with a flexible Project Structure (RCPSP-PS) is a generalization of the Resource Constrained Project Scheduling Problem (RCPSP). In the RCPSP, the goal is to determine a minimal makespan schedule subject to precedence and resource constraints. The generalization introduced in the RCPSP-PS is that, instead of executing all activities, only a subset of all activities has to be executed. We present a model that is based on two graphs: one representing precedence relations and one representing the activity selection structure. The latter defines which subset of activities has to be executed. Additionally, we present theoretical properties of this model and give an exact solution method that makes use of these properties by generating cutting planes and setting bounds on variables. Furthermore, three problem properties are introduced to classify problems in the literature. We compare our model to a model from literature on instances that possess a subset of these three problem properties and find a reduction in computing time. Furthermore, by comparing results on instances that possess all problem properties, it is shown that the computing times are decreased and better lower bounds are found by the cutting planes and variable bounds presented in this paper.
期刊介绍:
The European Journal of Operational Research (EJOR) publishes high quality, original papers that contribute to the methodology of operational research (OR) and to the practice of decision making.