{"title":"What makes the reconstruction of old residential buildings complex? A study in Vietnamese urban areas","authors":"Minh Van Nguyen, Khanh Duy Ha, Chien Thanh Phan","doi":"10.1108/ecam-03-2024-0300","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>Reconstruction of old buildings is often necessary after prolonged usage, but these projects encounter various complexities, leading to their failure. However, there is a lack of studies that focus on investigating the complexity of old building reconstruction initiatives. Thus, this study aims to examine the complexity of reconstruction projects for old buildings in Vietnamese urban areas.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>Through a literature review and discussions with experienced practitioners, 12 significant complexity factors were identified. The study then utilized the fuzzy decision-making trial and evaluation laboratory (DEMATEL) technique to analyze the interrelationships among these complexity factors.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>The findings revealed intricate interdependencies among the complexity factors, visualized in a complexity map. The map highlighted the critical complexities of site compensation, clearance and the long project duration. Furthermore, a causal diagram categorized the complexity factors into net-effect and net-cause groups.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>By examining the relationships and interactions among these factors, the study emphasizes the interconnected nature of complex systems and the influence of one factor on others. Therefore, decision-makers and stakeholders involved in reconstructing old buildings are suggested to possess a comprehensive understanding of these interdependencies to ensure effective decision-making.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":null,"pages":null},"PeriodicalIF":3.6000,"publicationDate":"2024-09-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-03-2024-0300","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0
Abstract
Purpose
Reconstruction of old buildings is often necessary after prolonged usage, but these projects encounter various complexities, leading to their failure. However, there is a lack of studies that focus on investigating the complexity of old building reconstruction initiatives. Thus, this study aims to examine the complexity of reconstruction projects for old buildings in Vietnamese urban areas.
Design/methodology/approach
Through a literature review and discussions with experienced practitioners, 12 significant complexity factors were identified. The study then utilized the fuzzy decision-making trial and evaluation laboratory (DEMATEL) technique to analyze the interrelationships among these complexity factors.
Findings
The findings revealed intricate interdependencies among the complexity factors, visualized in a complexity map. The map highlighted the critical complexities of site compensation, clearance and the long project duration. Furthermore, a causal diagram categorized the complexity factors into net-effect and net-cause groups.
Originality/value
By examining the relationships and interactions among these factors, the study emphasizes the interconnected nature of complex systems and the influence of one factor on others. Therefore, decision-makers and stakeholders involved in reconstructing old buildings are suggested to possess a comprehensive understanding of these interdependencies to ensure effective decision-making.
期刊介绍:
ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process.
ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.