Solutions to Complex Well-Testing Challenges Aid Offshore Black Sea Gasfield Development

C. Carpenter
{"title":"Solutions to Complex Well-Testing Challenges Aid Offshore Black Sea Gasfield Development","authors":"C. Carpenter","doi":"10.2118/0524-0078-jpt","DOIUrl":null,"url":null,"abstract":"\n \n This article, written by JPT Technology Editor Chris Carpenter, contains highlights of paper SPE 215123, “Frontiering Ultradeep Water Gas Field Development, Offshore Black Sea, Turkey: Solutions to Complex Well-Testing Challenges and Proving Production Potential,” by Coşan Ayan, SPE, Suat Aktepe, and Koscal Cig, Turkish Petroleum, et al. The paper has not been peer reviewed.\n \n \n \n Increasing demand for reliable energy resources has led to an increased exploration activity for untapped hydrocarbon resources in deep water. The recently discovered, fast-tracked Sakarya offshore natural gasfield development is a prime example. This paper describes dynamic reservoir characterization considerations, challenges, and engineering solutions to derisk field-development decisions, confirmed by a well-testing campaign in a complex setting with no tolerance for failure.\n \n \n \n The Sakarya field is approximately 170 km north of the Turkish coast in the Black Sea at 2117 m (Fig. 1). The natural gas field was discovered in August 2020 and is estimated to have potential natural gas reserves of 11 Tcf of lean gas, making it the largest gas reserve discovered in the Turkish Exclusive Economic Zone as well as the Black Sea.\n In October 2020, a second discovery was made in the lower sections of Tuna 1, which increased the potential recoverable reserve estimate to 14.3 Tcf of lean gas. The discovery was found at the deeper part of the well, where an additional 30 m of gas pay was encountered in the sandstone reservoir of the Late Miocene. Further, the drilling of the exploratory well Amasra 1, 40 km north of the Sakarya field, led to the discovery of 4.7 Tcf of gas in June 2021, and increased the potential recoverable cumulative natural gas reserves to 19 Tcf.\n The first gas production from the Sakarya gas field began in 2023 into the Turkish grid from the completed wells of the first phase of the project. To accelerate the time to first gas production, it was deemed necessary to flow-test the reservoirs to acquire critical reservoir information, assess production potential and completions efficiency, and reduce the number of wells. This was achieved by drilling and testing several appraisal wells with multiple target intervals that will be used later as producers.\n \n \n \n Formation-failure studies and wireline formation testing data have shown that these weak reservoirs are prone to sand production. As a result, downhole sand-exclusion completions are necessary. Gas permeabilities are good, with core-measured air permeabilities in the range of 1–1000 md. The reservoir pressure varies from 4,200 to 5,800 psi, depending on depth. Reservoir temperatures are relatively low, in the range of 25–60°C.\n Lower Completion Installation Sequences.\n After drilling, the main section was completed with 9⅞-in. 62.8-lbm/ft production casing. The selected interval from openhole logs and formation test results was perforated and overbalanced by individual runs of a tubing-conveyed perforation (TCP) system. On the second run, sump packers with direct wrap screens across the interval were installed and gravel was pumped. After the lower completion was in place and the drillstem test (DST) had been conducted, another part of the lower completion across the upper interval was installed and flow-tested. After completing all DST well tests, the well was suspended with the lower completion system in place, ready for installation of the upper completion with intelligent flow-control valves and permanent gauges.\n","PeriodicalId":16720,"journal":{"name":"Journal of Petroleum Technology","volume":"213 4","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-05-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Petroleum Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/0524-0078-jpt","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This article, written by JPT Technology Editor Chris Carpenter, contains highlights of paper SPE 215123, “Frontiering Ultradeep Water Gas Field Development, Offshore Black Sea, Turkey: Solutions to Complex Well-Testing Challenges and Proving Production Potential,” by Coşan Ayan, SPE, Suat Aktepe, and Koscal Cig, Turkish Petroleum, et al. The paper has not been peer reviewed. Increasing demand for reliable energy resources has led to an increased exploration activity for untapped hydrocarbon resources in deep water. The recently discovered, fast-tracked Sakarya offshore natural gasfield development is a prime example. This paper describes dynamic reservoir characterization considerations, challenges, and engineering solutions to derisk field-development decisions, confirmed by a well-testing campaign in a complex setting with no tolerance for failure. The Sakarya field is approximately 170 km north of the Turkish coast in the Black Sea at 2117 m (Fig. 1). The natural gas field was discovered in August 2020 and is estimated to have potential natural gas reserves of 11 Tcf of lean gas, making it the largest gas reserve discovered in the Turkish Exclusive Economic Zone as well as the Black Sea. In October 2020, a second discovery was made in the lower sections of Tuna 1, which increased the potential recoverable reserve estimate to 14.3 Tcf of lean gas. The discovery was found at the deeper part of the well, where an additional 30 m of gas pay was encountered in the sandstone reservoir of the Late Miocene. Further, the drilling of the exploratory well Amasra 1, 40 km north of the Sakarya field, led to the discovery of 4.7 Tcf of gas in June 2021, and increased the potential recoverable cumulative natural gas reserves to 19 Tcf. The first gas production from the Sakarya gas field began in 2023 into the Turkish grid from the completed wells of the first phase of the project. To accelerate the time to first gas production, it was deemed necessary to flow-test the reservoirs to acquire critical reservoir information, assess production potential and completions efficiency, and reduce the number of wells. This was achieved by drilling and testing several appraisal wells with multiple target intervals that will be used later as producers. Formation-failure studies and wireline formation testing data have shown that these weak reservoirs are prone to sand production. As a result, downhole sand-exclusion completions are necessary. Gas permeabilities are good, with core-measured air permeabilities in the range of 1–1000 md. The reservoir pressure varies from 4,200 to 5,800 psi, depending on depth. Reservoir temperatures are relatively low, in the range of 25–60°C. Lower Completion Installation Sequences. After drilling, the main section was completed with 9⅞-in. 62.8-lbm/ft production casing. The selected interval from openhole logs and formation test results was perforated and overbalanced by individual runs of a tubing-conveyed perforation (TCP) system. On the second run, sump packers with direct wrap screens across the interval were installed and gravel was pumped. After the lower completion was in place and the drillstem test (DST) had been conducted, another part of the lower completion across the upper interval was installed and flow-tested. After completing all DST well tests, the well was suspended with the lower completion system in place, ready for installation of the upper completion with intelligent flow-control valves and permanent gauges.
复杂试井挑战的解决方案有助于海上黑海气田开发
本文由 JPT 技术编辑 Chris Carpenter 撰写,包含 SPE 215123 号论文 "土耳其黑海近海超深水气田开发前沿 "的要点:该论文未经同行评审。 对可靠能源资源日益增长的需求导致了对深水未开发碳氢化合物资源勘探活动的增加。最近发现并快速推进的萨卡里亚海上天然气田开发就是一个典型的例子。本文介绍了动态储层特征描述的考虑因素、挑战和工程解决方案,以降低油田开发决策的风险,并通过在复杂环境中进行的油井测试活动加以证实。 Sakarya 气田位于黑海土耳其海岸以北约 170 公里处,海拔 2117 米(图 1)。该天然气田发现于 2020 年 8 月,预计潜在天然气储量为 11 Tcf(贫气),是土耳其专属经济区以及黑海发现的最大天然气储量。2020 年 10 月,在图纳 1 号的下部又有新发现,潜在可采储量估计增至 14.3 兆立方英尺贫气。该发现位于油井的深部,在晚中新世的砂岩储层中又发现了 30 米的含气量。此外,2021 年 6 月,在萨卡里亚气田以北 40 公里处钻探的 Amasra 1 号探井发现了 4.7 Tcf 的天然气,并将潜在可采累计天然气储量增加到 19 Tcf。萨卡里亚气田的首次天然气生产始于 2023 年,从项目第一阶段已完工的油井向土耳其电网供气。为了加快首次天然气生产的时间,我们认为有必要对储层进行流量测试,以获取关键的储层信息,评估生产潜力和完井效率,并减少油井数量。为此,钻探并测试了几口具有多个目标区间的评价井,这些井以后将作为生产井使用。 地层失效研究和有线地层测试数据表明,这些薄弱储层容易出砂。因此,必须进行井下排砂完井。天然气渗透率较高,岩心测量的空气渗透率在 1-1000 md 之间。储层压力介于 4,200 至 5,800 psi 之间,具体取决于深度。储层温度相对较低,在 25-60°C 之间。下部完井安装顺序。钻井结束后,主井段用 9 手英寸、62.8 磅米/英尺的钻杆完成钻井。62.8-lbm/ft 生产套管。根据裸眼井测井记录和地层测试结果,对选定的区间进行射孔,并通过油管输送射孔(TCP)系统的单次运行进行超平衡。在第二次作业中,安装了带直接包裹筛网的集液封隔器,并泵送砾石。下部完井就位并进行钻杆测试(DST)后,又安装了另一部分横跨上部间隔的下部完井,并进行了流量测试。完成所有 DST 油井测试后,油井暂停,下部完井系统就位,准备安装装有智能流量控制阀和永久压力表的上部完井系统。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
0.50
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信