Cetin Dam – stabilising troubled abutment slopes

Q4 Earth and Planetary Sciences
Mag. Irmina Pöschl, Dr. Johannes Kleberger, MSc. João Dinis, MSc. Teoman Hizal
{"title":"Cetin Dam – stabilising troubled abutment slopes","authors":"Mag. Irmina Pöschl,&nbsp;Dr. Johannes Kleberger,&nbsp;MSc. João Dinis,&nbsp;MSc. Teoman Hizal","doi":"10.1002/geot.202400007","DOIUrl":null,"url":null,"abstract":"<p>The 420 MW Cetin Dam Project in Turkey was subject to severe setbacks, including substantial geotechnical problems. Since 2011, several concessionaires, contractors and designers were involved. In June 2016, a major failure occurred at a high cut slope of the right bank (RB) valley flank. In 2017, contractor Limak took over the project with a US$ 600 mio concession contract. To secure the contractual agreement for state-guaranteed energy remuneration, Cetin Dam and hydro hydroelectric power plant (HEPP) had to be operative in 2020. Missing the time target would have implied high economic losses for the concessionaire, and this set-in-stone deadline imposed extraordinary pressure for developing fast and reliable solutions. Worryingly, progressing failure became evident at the failed RB cut slope, while rehabilitation works were ongoing. In late December 2017, shortly after a review of geotechnical conditions and slope design for the troubled RB slope had started, also parts of the left bank (LB) cut slope failed below crest level and threatened to grow into a global slope failure. With only 26 months’ time left for starting energy production, the slope instabilities jeopardised the economic success of the entire project. Within a 3-month emergency mission for both RB and LB slopes, a dedicated team succeeded in understanding the geotechnical problems, planning and implementing immediate mitigation measures, and developing design solutions. Operation of Cetin Dam and HEPP commenced in 2020.</p>","PeriodicalId":39412,"journal":{"name":"Geomechanik und Tunnelbau","volume":"17 3","pages":"184-194"},"PeriodicalIF":0.0000,"publicationDate":"2024-05-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Geomechanik und Tunnelbau","FirstCategoryId":"1085","ListUrlMain":"https://onlinelibrary.wiley.com/doi/10.1002/geot.202400007","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"Earth and Planetary Sciences","Score":null,"Total":0}
引用次数: 0

Abstract

The 420 MW Cetin Dam Project in Turkey was subject to severe setbacks, including substantial geotechnical problems. Since 2011, several concessionaires, contractors and designers were involved. In June 2016, a major failure occurred at a high cut slope of the right bank (RB) valley flank. In 2017, contractor Limak took over the project with a US$ 600 mio concession contract. To secure the contractual agreement for state-guaranteed energy remuneration, Cetin Dam and hydro hydroelectric power plant (HEPP) had to be operative in 2020. Missing the time target would have implied high economic losses for the concessionaire, and this set-in-stone deadline imposed extraordinary pressure for developing fast and reliable solutions. Worryingly, progressing failure became evident at the failed RB cut slope, while rehabilitation works were ongoing. In late December 2017, shortly after a review of geotechnical conditions and slope design for the troubled RB slope had started, also parts of the left bank (LB) cut slope failed below crest level and threatened to grow into a global slope failure. With only 26 months’ time left for starting energy production, the slope instabilities jeopardised the economic success of the entire project. Within a 3-month emergency mission for both RB and LB slopes, a dedicated team succeeded in understanding the geotechnical problems, planning and implementing immediate mitigation measures, and developing design solutions. Operation of Cetin Dam and HEPP commenced in 2020.

Cetin 大坝--加固有问题的台基斜坡
土耳其 420 兆瓦 Cetin 大坝项目遭遇严重挫折,包括大量岩土工程问题。自 2011 年以来,多个特许经营商、承包商和设计师参与其中。2016 年 6 月,右岸(RB)谷侧的高切坡发生了重大溃坝。2017 年,承包商 Limak 以 6 亿美元的特许权合同接管了该项目。为了确保国家保障能源报酬的合同协议,Cetin 大坝和水电站(HEPP)必须在 2020 年投入运营。如果不能按时完工,将给特许公司带来巨大的经济损失,而这一既定的最后期限也给开发快速可靠的解决方案带来了巨大压力。令人担忧的是,在修复工程进行的同时,RB 切坡的故障也在逐步显现。2017 年 12 月下旬,就在对出现问题的 RB 斜坡的岩土条件和斜坡设计进行审查后不久,左岸(LB)切坡的部分坡顶以下也出现了坍塌,并有可能发展成为整体斜坡坍塌。在距离开始能源生产仅剩 26 个月时间的情况下,边坡失稳危及整个项目的经济效益。在针对 RB 和 LB 斜坡为期 3 个月的紧急任务中,一支专业团队成功地了解了岩土工程问题,规划并立即实施了缓解措施,并制定了设计解决方案。Cetin 大坝和 HEPP 于 2020 年开始运行。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
Geomechanik und Tunnelbau
Geomechanik und Tunnelbau Earth and Planetary Sciences-Geotechnical Engineering and Engineering Geology
CiteScore
1.20
自引率
0.00%
发文量
111
期刊介绍: The contributions published in Geomechanics and Tunnelling deal with practical aspects of applied engineering geology, rock mechanics and rock engineering, soil mechanics and foundation engineering, and primarily tunnelling. Each issue focuses on a current topic or specific project. Brief news, reports from construction sites and news on conferences round off the content. From the start of 2009 Geomechanics and Tunnelling has been published as a bilingual English/German journal.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信