An Escalation System for Handling and Analyzing Production Disturbances

István Gödri
{"title":"An Escalation System for Handling and Analyzing Production Disturbances","authors":"István Gödri","doi":"10.3311/ppme.23004","DOIUrl":null,"url":null,"abstract":"In a manufacturing environment the effectiveness of internal problem solving is a key success factor in the service level performance offered to the customers. Broken internal processes need to be fixed immediately or at least in a very short time, in order to fulfill the committed delivery dates. There are several methodologies applied for internal problem solving used by different companies. This article presents a solution worked out for a plant operating in a high-mix low-volume (HMLV) production environment prone to both internal and external disruptions and disturbances. Principles, architecture and information flow in our digitized disruption handling – so-called escalation – system will be shortly discussed. Lessons learned in a six-year’s period of using the system will also be summarized. The recorded data confirm that with the introduction of the escalation system the capability of the plant to adapt to changing circumstances and disruptions greatly improved.","PeriodicalId":513310,"journal":{"name":"Periodica Polytechnica Mechanical Engineering","volume":"106 19","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-05-13","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Periodica Polytechnica Mechanical Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3311/ppme.23004","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

In a manufacturing environment the effectiveness of internal problem solving is a key success factor in the service level performance offered to the customers. Broken internal processes need to be fixed immediately or at least in a very short time, in order to fulfill the committed delivery dates. There are several methodologies applied for internal problem solving used by different companies. This article presents a solution worked out for a plant operating in a high-mix low-volume (HMLV) production environment prone to both internal and external disruptions and disturbances. Principles, architecture and information flow in our digitized disruption handling – so-called escalation – system will be shortly discussed. Lessons learned in a six-year’s period of using the system will also be summarized. The recorded data confirm that with the introduction of the escalation system the capability of the plant to adapt to changing circumstances and disruptions greatly improved.
处理和分析生产干扰的升级系统
在生产环境中,内部问题解决的有效性是影响客户服务水平的关键因素。需要立即或至少在很短的时间内修复损坏的内部流程,以履行承诺的交货日期。不同公司在解决内部问题时采用了多种方法。本文介绍了一个解决方案,该方案针对的是一家在高混合低产量(HMLV)生产环境中运行的工厂,这种生产环境容易受到内部和外部的破坏和干扰。下文将讨论我们的数字化中断处理系统(即所谓的升级系统)的原理、结构和信息流。此外,还将总结六年来使用该系统的经验教训。记录的数据证实,随着升级系统的引入,工厂适应不断变化的环境和中断的能力大大提高。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信