Malik Lakshan Hasantha, Anuradha Samarajeewa Waidyasekara, Hasith Chathuranga Victar
{"title":"Evaluation of time allocated for bid preparation in national competitive bidding in the Sri Lankan construction industry","authors":"Malik Lakshan Hasantha, Anuradha Samarajeewa Waidyasekara, Hasith Chathuranga Victar","doi":"10.1108/ecam-11-2023-1151","DOIUrl":null,"url":null,"abstract":"<h3>Purpose</h3>\n<p>Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for preparing a bid proposal as per the National Competitive Bidding (NCB) in the Sri Lankan context.</p><!--/ Abstract__block -->\n<h3>Design/methodology/approach</h3>\n<p>The study has adopted a mixed method approach and expert interviews and document review to detect, analyse and validate the issues, and solutions based on NCB along with the adequacy of the allocated bidding period used as main data collection tools. Both qualitative and quantitative data were analysed through manual content analysis and inferential analysis respectively.</p><!--/ Abstract__block -->\n<h3>Findings</h3>\n<p>Overall, 24 local issues with the existing competitive bidding process and solutions for each were identified. Among the 24 local issues, it was unanimously agreed by all interviewees that three specific issues require attention and improvement. These issues are related to the standard and incompleteness of bidding documents, inaccurate BOQ quantities measured by the consultant or the main contractor, and the excessive number of bidding document amendments by the consultant. It was revealed that a maximum of 42 calendar days (6 weeks) is sufficient for the bidding process while a minimum of 21 calendar days (3 weeks) is insufficient.</p><!--/ Abstract__block -->\n<h3>Originality/value</h3>\n<p>The findings of this study would be recommended that Information and Communication Technology Agency (ICTA) understand the necessity of revising the NCB reference to the time allocated for the preparation of bids. By recognising the importance of sufficient time allocation for bid preparation, this research serves as a practical guide for authorities involved in policy formulation, aiding them in implementing revisions that align with the dynamic requirements of bidding procedures.</p><!--/ Abstract__block -->","PeriodicalId":11888,"journal":{"name":"Engineering, Construction and Architectural Management","volume":"6 1","pages":""},"PeriodicalIF":3.6000,"publicationDate":"2024-04-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering, Construction and Architectural Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1108/ecam-11-2023-1151","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0
Abstract
Purpose
Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for preparing a bid proposal as per the National Competitive Bidding (NCB) in the Sri Lankan context.
Design/methodology/approach
The study has adopted a mixed method approach and expert interviews and document review to detect, analyse and validate the issues, and solutions based on NCB along with the adequacy of the allocated bidding period used as main data collection tools. Both qualitative and quantitative data were analysed through manual content analysis and inferential analysis respectively.
Findings
Overall, 24 local issues with the existing competitive bidding process and solutions for each were identified. Among the 24 local issues, it was unanimously agreed by all interviewees that three specific issues require attention and improvement. These issues are related to the standard and incompleteness of bidding documents, inaccurate BOQ quantities measured by the consultant or the main contractor, and the excessive number of bidding document amendments by the consultant. It was revealed that a maximum of 42 calendar days (6 weeks) is sufficient for the bidding process while a minimum of 21 calendar days (3 weeks) is insufficient.
Originality/value
The findings of this study would be recommended that Information and Communication Technology Agency (ICTA) understand the necessity of revising the NCB reference to the time allocated for the preparation of bids. By recognising the importance of sufficient time allocation for bid preparation, this research serves as a practical guide for authorities involved in policy formulation, aiding them in implementing revisions that align with the dynamic requirements of bidding procedures.
期刊介绍:
ECAM publishes original peer-reviewed research papers, case studies, technical notes, book reviews, features, discussions and other contemporary articles that advance research and practice in engineering, construction and architectural management. In particular, ECAM seeks to advance integrated design and construction practices, project lifecycle management, and sustainable construction. The journal’s scope covers all aspects of architectural design, design management, construction/project management, engineering management of major infrastructure projects, and the operation and management of constructed facilities. ECAM also addresses the technological, process, economic/business, environmental/sustainability, political, and social/human developments that influence the construction project delivery process.
ECAM strives to establish strong theoretical and empirical debates in the above areas of engineering, architecture, and construction research. Papers should be heavily integrated with the existing and current body of knowledge within the field and develop explicit and novel contributions. Acknowledging the global character of the field, we welcome papers on regional studies but encourage authors to position the work within the broader international context by reviewing and comparing findings from their regional study with studies conducted in other regions or countries whenever possible.