ANALYSIS OF TIME AND COST PERFORMANCE IN THE COMPLETION OF THE CONSTRUCTION PROJECT FOR THE REGIONAL DISASTER MANAGEMENT AGENCY (BPBD) BUILDING COMPLEX IN PASURUAN REGENCY, BUDGET YEAR 2023

Bagus Cahyono, Risma Marleno, W. Oetomo
{"title":"ANALYSIS OF TIME AND COST PERFORMANCE IN THE COMPLETION OF THE CONSTRUCTION PROJECT FOR THE REGIONAL DISASTER MANAGEMENT AGENCY (BPBD) BUILDING COMPLEX IN PASURUAN REGENCY, BUDGET YEAR 2023","authors":"Bagus Cahyono, Risma Marleno, W. Oetomo","doi":"10.55047/marginal.v3i2.1039","DOIUrl":null,"url":null,"abstract":"In the construction project of the Pasuruan Regency BPBD building complex, which is currently still ongoing, has experienced problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities, where the results of the progress realization are not in accordance with the schedule plan, through this writing an evaluation is carried out related to performance in the field through an approach using. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP, the calculation of cost indicators consists of calculating the CV value, Cost Performance Index (CPI), ETC and EAC, and also calculating related to time indicators including calculating the SV value, Time Performance Index (SPI) and also calculating the time requirements / Estimated time (TE) in project completion. Based the results of  calculation / data analysis that has been carried out, the Cost Performance Index value CPI> 1 is obtained, and the SPI Time Performance Index value < 1, indicating that the realization cost is still below the plan cost with the achievement of progress realization which is also still below the plan schedule. while for the ETC value of project completion of Rp.2,148,176,877,000..148,176,877.17 with an EAC value of Rp.16,624,276,448.77 from the total contract value of Rp. 18,898,770,576.77. and related to the estimated time requirement for project completion (TE) obtained a time of 220.75 ⁓ 221 days, 11 days later than the time provided 210 days.","PeriodicalId":471269,"journal":{"name":"MARGINAL JOURNAL OF MANAGEMENT ACCOUNTING GENERAL FINANCE AND INTERNATIONAL ECONOMIC ISSUES","volume":"60 4","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2024-01-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"MARGINAL JOURNAL OF MANAGEMENT ACCOUNTING GENERAL FINANCE AND INTERNATIONAL ECONOMIC ISSUES","FirstCategoryId":"0","ListUrlMain":"https://doi.org/10.55047/marginal.v3i2.1039","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

In the construction project of the Pasuruan Regency BPBD building complex, which is currently still ongoing, has experienced problems related to the schedule for the implementation of its activities. The problem in question is the delay in the schedule for the implementation of its activities, where the results of the progress realization are not in accordance with the schedule plan, through this writing an evaluation is carried out related to performance in the field through an approach using. The data analysis process is carried out by calculating analysis indicators including BCWS, BCWP and ACWP, the calculation of cost indicators consists of calculating the CV value, Cost Performance Index (CPI), ETC and EAC, and also calculating related to time indicators including calculating the SV value, Time Performance Index (SPI) and also calculating the time requirements / Estimated time (TE) in project completion. Based the results of  calculation / data analysis that has been carried out, the Cost Performance Index value CPI> 1 is obtained, and the SPI Time Performance Index value < 1, indicating that the realization cost is still below the plan cost with the achievement of progress realization which is also still below the plan schedule. while for the ETC value of project completion of Rp.2,148,176,877,000..148,176,877.17 with an EAC value of Rp.16,624,276,448.77 from the total contract value of Rp. 18,898,770,576.77. and related to the estimated time requirement for project completion (TE) obtained a time of 220.75 ⁓ 221 days, 11 days later than the time provided 210 days.
2023 预算年度帕苏鲁安地区灾害管理机构(BPBD)综合大楼建设项目完工时间和成本绩效分析
目前仍在进行中的 Pasuruan 地区 BPBD 建筑群建设项目在活动实施进度方面遇到了问题。问题在于活动实施进度的延迟,进度实现的结果与进度计划不符。数据分析过程通过计算包括 BCWS、BCWP 和 ACWP 在内的分析指标来进行,成本指标的计算包括计算 CV 值、成本绩效指数(CPI)、ETC 和 EAC,还包括计算 SV 值、时间绩效指数(SPI)以及计算项目完成的时间要求/预计时间(TE)等相关时间指标。根据已进行的计算/数据分析结果,成本绩效指数值 CPI> 1,SPI 时间绩效指数值 < 1,表明实现成本仍低于计划成本,而实现进度也仍低于计划进度。148,176,877.17 印尼盾,EAC 值为 16,624,276,448.77 印尼盾,合同总值为 18,898,770,576.77 印尼盾。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书