{"title":"A study on time schedules for construction projects in Hanoi, Vietnam","authors":"D. Hai","doi":"10.24425/ace.2024.148935","DOIUrl":null,"url":null,"abstract":"With its position as the capital, Hanoi is the political center as well as the second largest economic center of the country. Therefore, the city is always allocated a large budget in construction investment to create material facilities for political tasks and economic and social development. During the implementation of construction projects, a number of difficulties and limitations have appeared. In which, projects are delayed in construction and disbursement, reducing investment efficiency and not meeting the expectations of the government and people. From this fact, the authors have conducted a study to evaluate the causes affecting the time schedule of construction projects in Hanoi. The method F-APH (Fuzzy Analytic Hierarchy Process) was used to analyze data objectively and accurately about the causes affecting the time schedule. From there, these causes are classified into groups of subjective causes (from within the project) and groups of objective causes (from outside the project). The results show that subjective causes, originating from project participants, have a stronger influence than objective causes. A number of specific proposals to the actors involved in construction projects are made to eliminate or limit the impact of the causes of construction progress.","PeriodicalId":45753,"journal":{"name":"Archives of Civil Engineering","volume":null,"pages":null},"PeriodicalIF":1.1000,"publicationDate":"2024-03-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Archives of Civil Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24425/ace.2024.148935","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
引用次数: 0
Abstract
With its position as the capital, Hanoi is the political center as well as the second largest economic center of the country. Therefore, the city is always allocated a large budget in construction investment to create material facilities for political tasks and economic and social development. During the implementation of construction projects, a number of difficulties and limitations have appeared. In which, projects are delayed in construction and disbursement, reducing investment efficiency and not meeting the expectations of the government and people. From this fact, the authors have conducted a study to evaluate the causes affecting the time schedule of construction projects in Hanoi. The method F-APH (Fuzzy Analytic Hierarchy Process) was used to analyze data objectively and accurately about the causes affecting the time schedule. From there, these causes are classified into groups of subjective causes (from within the project) and groups of objective causes (from outside the project). The results show that subjective causes, originating from project participants, have a stronger influence than objective causes. A number of specific proposals to the actors involved in construction projects are made to eliminate or limit the impact of the causes of construction progress.
期刊介绍:
ARCHIVES OF CIVIL ENGINEERING publish original papers of the theoretical, experimental, numerical and practical nature in the fields of structural mechanics, soil mechanics and foundations engineering, concrete, metal, timber and composite polymer structures, hydrotechnical structures, roads, railways and bridges, building services, building physics, management in construction, production of construction materials, construction of civil engineering structures, education of civil engineers.