Comparative Study of Plug and Abandonment Using Balanced Plug Cementing Method: Case Study of Well “NV-01” Field “NS”

Krt. Nur Suhascaryo, Ciiqa Ciiqa, Andi Novita Mama Anugrah
{"title":"Comparative Study of Plug and Abandonment Using Balanced Plug Cementing Method: Case Study of Well “NV-01” Field “NS”","authors":"Krt. Nur Suhascaryo, Ciiqa Ciiqa, Andi Novita Mama Anugrah","doi":"10.29017/scog.46.2.1502","DOIUrl":null,"url":null,"abstract":"The NOV-01 well is a directional well that has technical problems (fish), namely the stuck pipe problem and the problem of high land use operational costs. Based on the results of the evaluation of the economic and risk technical aspects, a plug abandonment (PA) was carried out for the NOV-01 well. The purpose of this research is to compare the 3 stages and 5 stages in PA work and their influence on work program planning and budgeting. The research methodology is qualitative and quantitative. The NOV-01 well plug abandonment activity is carried out by preparing a work program plan such as determining the depth interval of the well to be plugged, the volume of cement slurry additives, as well as the rig method which all refer to the existing standards and regulations, namely SNI 13-6910-2002 and NORSOK D-010. The results of a comparative study on PA planning at 3 stages required 279 sacks of cement and 450 sacks of cement at 5 stages with a density of 15.8 ppg. PA on well NOV-01 uses the rig method with a capacity of 450 HP. For 3 stages it takes 9 days and 5 stages for 11 days. Comparison of estimated costs for PA of NOV-01 well, namely 3 stages of IDR 6,062,977,890.31- and 5 stages of IDR 8,374,824,218.62-. Well NOV-01, PA which is suitable is 5 stages because there is an overpressured zone so that the cement plug is isolated.","PeriodicalId":21649,"journal":{"name":"Scientific Contributions Oil and Gas","volume":"80 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Scientific Contributions Oil and Gas","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29017/scog.46.2.1502","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The NOV-01 well is a directional well that has technical problems (fish), namely the stuck pipe problem and the problem of high land use operational costs. Based on the results of the evaluation of the economic and risk technical aspects, a plug abandonment (PA) was carried out for the NOV-01 well. The purpose of this research is to compare the 3 stages and 5 stages in PA work and their influence on work program planning and budgeting. The research methodology is qualitative and quantitative. The NOV-01 well plug abandonment activity is carried out by preparing a work program plan such as determining the depth interval of the well to be plugged, the volume of cement slurry additives, as well as the rig method which all refer to the existing standards and regulations, namely SNI 13-6910-2002 and NORSOK D-010. The results of a comparative study on PA planning at 3 stages required 279 sacks of cement and 450 sacks of cement at 5 stages with a density of 15.8 ppg. PA on well NOV-01 uses the rig method with a capacity of 450 HP. For 3 stages it takes 9 days and 5 stages for 11 days. Comparison of estimated costs for PA of NOV-01 well, namely 3 stages of IDR 6,062,977,890.31- and 5 stages of IDR 8,374,824,218.62-. Well NOV-01, PA which is suitable is 5 stages because there is an overpressured zone so that the cement plug is isolated.
使用平衡堵塞固井法进行堵塞和废弃的比较研究:NV-01 井案例研究油田 "NS
NOV-01 井是一口定向井,存在技术问题(鱼),即卡管问题和土地使用运营成本高的问题。根据经济和风险技术方面的评估结果,对 NOV-01 井进行了堵塞弃井(PA)。本研究的目的是比较 PA 工作的 3 个阶段和 5 个阶段及其对工作计划规划和预算编制的影响。研究方法是定性和定量相结合。NOV-01 井的堵漏废弃活动是通过编制工作方案计划来进行的,例如确定要堵漏的井深间隔、水泥浆添加剂的用量以及钻机方法,这些都要参照现有的标准和规定,即 SNI 13-6910-2002 和 NORSOK D-010。对 3 个阶段的 PA 规划进行比较研究的结果显示,需要 279 袋水泥,而 5 个阶段需要 450 袋水泥,密度为 15.8 ppg。NOV-01 井的 PA 采用钻机法,功率为 450 HP。3 个阶段需要 9 天,5 个阶段需要 11 天。NOV-01 号井 PA 的估计成本比较,即 3 级 6,062,977,890.31 印尼盾和 5 级 8,374,824,218.62 印尼盾。NOV-01 井适合采用 5 级 PA,因为该井存在超压区,水泥塞被隔离。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
CiteScore
0.50
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信