Analysis of Labor Productivity in Bricklaying Operation of Building Construction in Surkhet, Nepal

Bijay Rana, Socrates Bhattarai Sharma, Uttam Neupane, Santosh Kumar Shrestha
{"title":"Analysis of Labor Productivity in Bricklaying Operation of Building Construction in Surkhet, Nepal","authors":"Bijay Rana, Socrates Bhattarai Sharma, Uttam Neupane, Santosh Kumar Shrestha","doi":"10.3126/aet.v3i1.60628","DOIUrl":null,"url":null,"abstract":"The development of the nation’s infrastructure depends heavily on the construction industry. The entire labor productivity during the project has a significant impact on construction productivity. Therefore, it is necessary to investigate the origins and consequences of labor productivity in the context of the Nepalese construction industry. The methodology involved in conducting the research is the formation of the problem statement, developing research objectives, literature review, data collection, data analysis, conclusion, and recommendations. The data for this research is collected by a literature review as well as a questionnaire and physical observations of building construction. The literature review helped to identify several elements that have an impact on labor productivity. To determine the factors that influenced labor productivity the most, a questionnaire survey was undertaken with a Likert scale. The required information was then produced by processing, analyzing, and interpreting the data using Microsoft Excel and SPSS software tools. The Cronbach’s Alpha value was computed using SPSS to measure the internal consistency and found to be 0.976 which shows the better reliability of the research and data collection. From the study, we can conclude that the results obtained from the relative importance index (RII), mean response analysis (MRA), and sensitivity analysis through Artificial Neural Network (ANN) meets the same conclusion as the highest influencing factor affecting labor productivity is ‘Material related factors’ followed by ‘Leadership related factors’, ‘Manpower related factors’, and the last ‘Other factors’.","PeriodicalId":350557,"journal":{"name":"Advances in Engineering and Technology: An International Journal","volume":"94 5","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-12-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Advances in Engineering and Technology: An International Journal","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3126/aet.v3i1.60628","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The development of the nation’s infrastructure depends heavily on the construction industry. The entire labor productivity during the project has a significant impact on construction productivity. Therefore, it is necessary to investigate the origins and consequences of labor productivity in the context of the Nepalese construction industry. The methodology involved in conducting the research is the formation of the problem statement, developing research objectives, literature review, data collection, data analysis, conclusion, and recommendations. The data for this research is collected by a literature review as well as a questionnaire and physical observations of building construction. The literature review helped to identify several elements that have an impact on labor productivity. To determine the factors that influenced labor productivity the most, a questionnaire survey was undertaken with a Likert scale. The required information was then produced by processing, analyzing, and interpreting the data using Microsoft Excel and SPSS software tools. The Cronbach’s Alpha value was computed using SPSS to measure the internal consistency and found to be 0.976 which shows the better reliability of the research and data collection. From the study, we can conclude that the results obtained from the relative importance index (RII), mean response analysis (MRA), and sensitivity analysis through Artificial Neural Network (ANN) meets the same conclusion as the highest influencing factor affecting labor productivity is ‘Material related factors’ followed by ‘Leadership related factors’, ‘Manpower related factors’, and the last ‘Other factors’.
尼泊尔苏尔凯特建筑施工砌砖作业的劳动生产率分析
国家基础设施的发展在很大程度上依赖于建筑业。项目期间的整个劳动生产率对建筑业的生产率有重大影响。因此,有必要以尼泊尔建筑业为背景,调查劳动生产率的起源和后果。开展研究的方法包括形成问题陈述、制定研究目标、文献综述、数据收集、数据分析、结论和建议。本研究的数据是通过文献综述、问卷调查和对建筑施工的实际观察收集的。文献综述有助于确定对劳动生产率有影响的几个因素。为确定对劳动生产率影响最大的因素,采用李克特量表进行了问卷调查。然后使用 Microsoft Excel 和 SPSS 软件工具对数据进行处理、分析和解释,从而得出所需的信息。我们使用 SPSS 计算了 Cronbach's Alpha 值,以衡量内部一致性,结果发现 Cronbach's Alpha 值为 0.976,这表明研究和数据收集具有较好的可靠性。通过这项研究,我们可以得出结论,从相对重要性指数(RII)、平均响应分析(MRA)以及通过人工神经网络(ANN)进行的敏感性分析得出的结果符合相同的结论,即影响劳动生产率的最高影响因素是 "材料相关因素",其次是 "领导相关因素"、"人力相关因素",最后是 "其他因素"。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信