Priority Handling of Teurebeh Irrigation Assets, Aceh Besar District, Aceh Province

Azmeri Azmeri, Beryl Choliq Ar-rahman, Faris Zahran Jemi, Cut Dwi Refika, Nina Shaskia
{"title":"Priority Handling of Teurebeh Irrigation Assets, Aceh Besar District, Aceh Province","authors":"Azmeri Azmeri, Beryl Choliq Ar-rahman, Faris Zahran Jemi, Cut Dwi Refika, Nina Shaskia","doi":"10.13170/aijst.12.2.28575","DOIUrl":null,"url":null,"abstract":"Teurebeh Irrigation scheme is one of the promising irrigation areas in Aceh Besar District, Aceh Province. It is also one of the buffers in the agricultural sector, covering 750 hectares of agricultural area. However, the construction has shrunk over time, and the evaluation at the end of 2020 classified it as \"Poor Performance and Requiring Attention.\" This study aims to determine the handling priority for the irrigation networks at the Teurebeh Irrigation scheme. Data on irrigation network inventory was used as input. The determination of handling priority was conducted using the Mann-Whitney method. The ranking for determining the importance of irrigation assets is based on the condition and function of the irrigation assets. ArcGIS and Google Earth software were used to determine the condition and handling of all assets. The results show that the handling priority levels are between the primary and secondary channels. The tapping structure of BDT.8, BDT.6, BDT.4, BDT.1, and BDT.7 are ranked 1 to 5, meaning they must be fixed immediately as the conditions are severe to moderately damaged and not functioning to functioning poorly. BDT.1 to BDT.3 is in the Primary Channel, while BDT.4 to BDT.8 is in the Secondary Channel. The handling priority for irrigation construction in the primary channel (BDT.1, BDT.1a, and BDT.1c) and the secondary channel (BDT.8, BDT.6, and BDT.7a) are within priority 1 to 3. The Mann-Whitney test on the proposed hypothesis comparing the urgency level between the two channels is insignificant, indicating no significant difference between the handling of primary and secondary channels, as both have similar conditions and functions. The results are expected to contribute to decision-making at the Irrigation Department in designing proposals for renovating irrigation networks.","PeriodicalId":7128,"journal":{"name":"Aceh International Journal of Science and Technology","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2023-08-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Aceh International Journal of Science and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.13170/aijst.12.2.28575","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Teurebeh Irrigation scheme is one of the promising irrigation areas in Aceh Besar District, Aceh Province. It is also one of the buffers in the agricultural sector, covering 750 hectares of agricultural area. However, the construction has shrunk over time, and the evaluation at the end of 2020 classified it as "Poor Performance and Requiring Attention." This study aims to determine the handling priority for the irrigation networks at the Teurebeh Irrigation scheme. Data on irrigation network inventory was used as input. The determination of handling priority was conducted using the Mann-Whitney method. The ranking for determining the importance of irrigation assets is based on the condition and function of the irrigation assets. ArcGIS and Google Earth software were used to determine the condition and handling of all assets. The results show that the handling priority levels are between the primary and secondary channels. The tapping structure of BDT.8, BDT.6, BDT.4, BDT.1, and BDT.7 are ranked 1 to 5, meaning they must be fixed immediately as the conditions are severe to moderately damaged and not functioning to functioning poorly. BDT.1 to BDT.3 is in the Primary Channel, while BDT.4 to BDT.8 is in the Secondary Channel. The handling priority for irrigation construction in the primary channel (BDT.1, BDT.1a, and BDT.1c) and the secondary channel (BDT.8, BDT.6, and BDT.7a) are within priority 1 to 3. The Mann-Whitney test on the proposed hypothesis comparing the urgency level between the two channels is insignificant, indicating no significant difference between the handling of primary and secondary channels, as both have similar conditions and functions. The results are expected to contribute to decision-making at the Irrigation Department in designing proposals for renovating irrigation networks.
优先处理亚齐省亚齐Besar地区的Teurebeh灌溉资产
Teurebeh灌溉计划是亚齐省亚齐Besar地区有前途的灌溉地区之一。它也是农业部门的缓冲区之一,占地750公顷的农业面积。然而,随着时间的推移,建设规模逐渐缩小,2020年底的评估将其列为“表现不佳,需要关注”。本研究旨在确定Teurebeh灌溉计划中灌溉网络的处理优先级。灌溉网络清查数据作为输入。采用曼-惠特尼法确定处理优先级。确定灌溉资产重要性排序的依据是灌溉资产的状况和功能。使用ArcGIS和Google Earth软件确定所有资产的状况和处理。结果表明,处理优先级介于主通道和辅助通道之间。BDT.8、BDT.6、BDT.4、BDT.1、BDT.7的攻口结构被列为1到5级,这意味着它们必须立即修复,因为它们的情况是严重到中度受损,而不是功能不佳。BDT.1 ~ BDT.3在主通道,BDT.4 ~ BDT.8在从通道。主渠(BDT.1、BDT.1a、BDT.1c)和次渠(BDT.8、BDT.6、BDT.7a)灌溉施工的处理优先级在1 ~ 3级。对所提出的假设进行的Mann-Whitney检验比较两个渠道之间的紧急程度是不显著的,表明主渠道和次级渠道的处理没有显著差异,因为它们具有相似的条件和功能。预期其结果将有助于灌溉部门在设计改造灌溉网络的建议方面作出决策。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
19
审稿时长
8 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信