Scope and exceptions to acceptance Adjudication Prior to Compensation

Jun Seob Shin
{"title":"Scope and exceptions to acceptance Adjudication Prior to Compensation","authors":"Jun Seob Shin","doi":"10.12972/cudla.20230010","DOIUrl":null,"url":null,"abstract":"The Supreme Court has ruled that compensation for land acquisition and for public projects under the Act on Acquisition and Compensation of Land for Public Works Projects must be adjudicated by the Land Tribunal. It has been determined that compensation claimants cannot directly claim compensation from the project operator without following the adjudication process. This rationale, known as the principle of “adjudication prior to compensation” has been gradually extended to areas such as business compensation, agricultural compensation, as well as compensation for livelihoods. At the same time, the Supreme Court has indicated that for compensation items such as relocation expenses and moving costs within the category of compensation for livelihoods, the principle of adjudication prior to compensation does not apply. This implies that affected parties can directly claim compensation through individual lawsuits without waiting for the Land Tribunal's adjudication, or the project operator can proceed with compensation according to the Land Compensation Act. When comparing the legal nature of compensation categories such as business compensation and agricultural compensation, where the principle of adjudication prior to compensation applies, with categories such as relocation expenses and moving costs, it becomes evident that they all fall under indirect compensation for livelihoods. There is little relevance between the application of the principle of reconsideration prior to compensation and the issue of whether appraisal is required for compensation. This clarifies that the scope of application of the principle of adjudication prior to compensation is determined not by the legal nature or characteristics of compensation categories, but by the Supreme Court's judgment aimed at resolving fundamental inconsistencies between the land compensation system and the practice to achieve concrete validity. Based on the Supreme Court's principle of adjudication prior to compensation, to unify the compensation process for all land compensation categories, including items such as relocation expenses, it becomes necessary to interpret the scope of “adjudication” more expansively within the principle of adjudication prior to compensation. This may involve interpreting Article 50, Paragraph 1, Subparagraph 2 of the Land Compensation Act to allow the Land Tribunal to make increased adjudication for “loss compensation,” even without individual applications for adjudication, to account for items such as relocation expenses. However, this would still necessitate changing existing practical norms and procedures. Considering these points, the Supreme Court's principle of adjudication prior to compensation appears to be applicable only in specific circumstances, and extending it to the entire land compensation process seems impractical.","PeriodicalId":479735,"journal":{"name":"Construction & Urban Development Law Association","volume":"37 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-09-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Construction & Urban Development Law Association","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12972/cudla.20230010","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The Supreme Court has ruled that compensation for land acquisition and for public projects under the Act on Acquisition and Compensation of Land for Public Works Projects must be adjudicated by the Land Tribunal. It has been determined that compensation claimants cannot directly claim compensation from the project operator without following the adjudication process. This rationale, known as the principle of “adjudication prior to compensation” has been gradually extended to areas such as business compensation, agricultural compensation, as well as compensation for livelihoods. At the same time, the Supreme Court has indicated that for compensation items such as relocation expenses and moving costs within the category of compensation for livelihoods, the principle of adjudication prior to compensation does not apply. This implies that affected parties can directly claim compensation through individual lawsuits without waiting for the Land Tribunal's adjudication, or the project operator can proceed with compensation according to the Land Compensation Act. When comparing the legal nature of compensation categories such as business compensation and agricultural compensation, where the principle of adjudication prior to compensation applies, with categories such as relocation expenses and moving costs, it becomes evident that they all fall under indirect compensation for livelihoods. There is little relevance between the application of the principle of reconsideration prior to compensation and the issue of whether appraisal is required for compensation. This clarifies that the scope of application of the principle of adjudication prior to compensation is determined not by the legal nature or characteristics of compensation categories, but by the Supreme Court's judgment aimed at resolving fundamental inconsistencies between the land compensation system and the practice to achieve concrete validity. Based on the Supreme Court's principle of adjudication prior to compensation, to unify the compensation process for all land compensation categories, including items such as relocation expenses, it becomes necessary to interpret the scope of “adjudication” more expansively within the principle of adjudication prior to compensation. This may involve interpreting Article 50, Paragraph 1, Subparagraph 2 of the Land Compensation Act to allow the Land Tribunal to make increased adjudication for “loss compensation,” even without individual applications for adjudication, to account for items such as relocation expenses. However, this would still necessitate changing existing practical norms and procedures. Considering these points, the Supreme Court's principle of adjudication prior to compensation appears to be applicable only in specific circumstances, and extending it to the entire land compensation process seems impractical.
补偿前的接受裁决的范围和例外
最高法院裁定,根据《公共工程项目土地征用和补偿法》对土地征用和公共项目的补偿必须由土地法庭裁决。已经确定,赔偿索赔人不能在不遵循裁决程序的情况下直接向项目运营商索赔。这一被称为“先审后赔”原则的理论基础已逐渐扩展到商业赔偿、农业赔偿以及生计赔偿等领域。与此同时,大法院表示,对于生活补偿范畴内的搬迁费、搬家费等补偿项目,不适用先裁决后补偿的原则。这意味着,受影响方可以直接通过个人诉讼要求赔偿,而无需等待土地法庭的裁决,或者项目运营商可以根据《土地补偿法》进行赔偿。将先审后赔原则适用的企业补偿、农业补偿等补偿类别与搬迁费用、搬迁费用等补偿类别的法律性质进行比较,可以明显看出,它们都属于间接生计补偿。在赔偿之前重新考虑的原则的适用与赔偿是否需要评估的问题之间几乎没有关系。这就明确了先审后赔原则的适用范围不是由赔偿类别的法律性质或特征决定的,而是由最高法院为解决土地补偿制度与实践之间的根本矛盾而作出的判决来实现具体效力的。根据大法院先审后赔的原则,为了统一包括搬迁费等项目在内的所有土地补偿类别的补偿程序,有必要在先审后赔的原则下对“裁决”的范围进行更广泛的解释。这可能涉及对《土地赔偿法》第五十条第一项第二款的解释,允许土地审裁处在没有个人申请裁定的情况下,增加对“损失赔偿”的裁定,以考虑搬迁费用等项目。但是,这仍然需要改变现有的实际规范和程序。考虑到这些问题,最高法院的先审后赔原则似乎只适用于特定情况,将其推广到整个土地补偿过程似乎不切实际。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信