The World's First Offshore Multilateral Well Completed with Multistage Proppant Fracturing: A Case Study from Offshore Black Sea

A. Tomlins, J. Conrad, Bogdan Bocaneala
{"title":"The World's First Offshore Multilateral Well Completed with Multistage Proppant Fracturing: A Case Study from Offshore Black Sea","authors":"A. Tomlins, J. Conrad, Bogdan Bocaneala","doi":"10.2118/194324-MS","DOIUrl":null,"url":null,"abstract":"\n The paper aims to present the successful execution of the first offshore multilateral well completed for multistage high-pressure proppant stimulation - in the Black Sea, offshore Romania. The paper describes the drivers that lead the operator to trial a multilateral well as well as cover the considerations made in selecting, defining and executing the final completion solution with a review of the lessons learned.\n With only one platform slot left and a significant undrained area of reservoir the operator had to maximise the hydrocarbon recovery through a single well which, due to pressure to increase the operator's daily production, had to be finalised in just one year. Building on field experience gained since 2008 in drilling and completing for multistage proppant stimulation a detailed screening and evaluation of multilateral completion technologies was performed. The focus was on developing a concept that would minimise risks during execution while meeting cost and lead time objectives, which necessitated customising the chosen TAML Level 3 completion design and installation methodology.\n To maximise rig-time efficiency the well was executed in two phases: 1) drilling and lower completion installation of both branches with a drilling rig and 2) stimulation and upper completion installation with the platform's workover rig. With six stages in each lateral the high-pressure stimulation was executed by a converted supply vessel in four sailings, necessary to reload materials. To meet the delivery schedule, ensure simplicity and utilise operator experience the completion was realised with no dedicated multilateral hardware, rather, through the effective use of standard multistage stimulation open hole completion equipment and appropriately engineered bent joints to exit the main bore.\n With initial production rates higher than anticipated, the multilateral well completed in this manner has proven to be considerably more economic than drilling two horizontal wells with equivalent reservoir coverage. The success of this well serves as a proof of concept and provides increased confidence in delivering reliable, cost effective multilateral wells even under tight time constraints and in areas and/or operators with no history of multilateral well completions","PeriodicalId":103693,"journal":{"name":"Day 2 Wed, February 06, 2019","volume":"42 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-01-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, February 06, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/194324-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The paper aims to present the successful execution of the first offshore multilateral well completed for multistage high-pressure proppant stimulation - in the Black Sea, offshore Romania. The paper describes the drivers that lead the operator to trial a multilateral well as well as cover the considerations made in selecting, defining and executing the final completion solution with a review of the lessons learned. With only one platform slot left and a significant undrained area of reservoir the operator had to maximise the hydrocarbon recovery through a single well which, due to pressure to increase the operator's daily production, had to be finalised in just one year. Building on field experience gained since 2008 in drilling and completing for multistage proppant stimulation a detailed screening and evaluation of multilateral completion technologies was performed. The focus was on developing a concept that would minimise risks during execution while meeting cost and lead time objectives, which necessitated customising the chosen TAML Level 3 completion design and installation methodology. To maximise rig-time efficiency the well was executed in two phases: 1) drilling and lower completion installation of both branches with a drilling rig and 2) stimulation and upper completion installation with the platform's workover rig. With six stages in each lateral the high-pressure stimulation was executed by a converted supply vessel in four sailings, necessary to reload materials. To meet the delivery schedule, ensure simplicity and utilise operator experience the completion was realised with no dedicated multilateral hardware, rather, through the effective use of standard multistage stimulation open hole completion equipment and appropriately engineered bent joints to exit the main bore. With initial production rates higher than anticipated, the multilateral well completed in this manner has proven to be considerably more economic than drilling two horizontal wells with equivalent reservoir coverage. The success of this well serves as a proof of concept and provides increased confidence in delivering reliable, cost effective multilateral wells even under tight time constraints and in areas and/or operators with no history of multilateral well completions
世界上第一口海上多级支撑剂压裂完井——以黑海海上为例
本文旨在介绍罗马尼亚黑海海域首口海上多级高压支撑剂增产井的成功实施情况。本文介绍了导致作业者进行多分支井试验的驱动因素,以及在选择、定义和执行最终完井解决方案时所考虑的因素,并总结了经验教训。由于只剩下一个平台槽,并且有很大的油藏未排水区域,运营商必须通过单口井最大限度地提高油气采收率,由于增加运营商日产量的压力,必须在短短一年内完成。基于2008年以来多级支撑剂增产钻井和完井的现场经验,对多级完井技术进行了详细的筛选和评估。重点是开发一种概念,在满足成本和交货时间目标的同时,将执行过程中的风险降到最低,这就需要定制所选择的TAML Level 3完井设计和安装方法。为了最大限度地提高钻机时间效率,该井分两个阶段进行:1)使用钻机对两个分支进行钻井和下部完井安装;2)使用平台的修井机进行增产和上部完井安装。高压增产作业由一艘改装的补给船执行,每段作业有6个阶段,需要进行4次装填。为了满足交付计划,确保简单性和利用操作人员的经验,完成完井没有专用的多硬件,而是通过有效使用标准多级增产裸眼完井设备和适当设计的弯曲接头来退出主井眼。由于初始产量高于预期,以这种方式完井的多边井已被证明比钻两口同等油藏覆盖的水平井要经济得多。这口井的成功证明了这一概念,并增加了在时间紧迫的情况下,以及在没有多边井完井历史的地区和/或运营商中,交付可靠、经济高效的多边井的信心
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信