Investigation of performance degradation for TNB newly commissioned combined cycle power plant Case study at PD1, Tuanku Jaafar Power Station, Port Dickson

C. H. Lee, Z. A. Mamat
{"title":"Investigation of performance degradation for TNB newly commissioned combined cycle power plant Case study at PD1, Tuanku Jaafar Power Station, Port Dickson","authors":"C. H. Lee, Z. A. Mamat","doi":"10.1109/ICEENVIRON.2009.5398657","DOIUrl":null,"url":null,"abstract":"Phase 1 of Tuanku Jaafar Power Station, Port Dickson (PD1) is one of the newest power plants in Tenaga Nasional Berhad (TNB). This combined cycle plant with the nominal capacity of 750MW started its commercial operation in 2005. However, in less than 2 years of its operation, the plant has indicated significant capacity degradation. Consequently, TNB carried few investigations to determine the cause for the capacity degradation. This paper describes the approach taken and the outcomes of the investigations.","PeriodicalId":211736,"journal":{"name":"2009 3rd International Conference on Energy and Environment (ICEE)","volume":"108 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2009 3rd International Conference on Energy and Environment (ICEE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICEENVIRON.2009.5398657","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Phase 1 of Tuanku Jaafar Power Station, Port Dickson (PD1) is one of the newest power plants in Tenaga Nasional Berhad (TNB). This combined cycle plant with the nominal capacity of 750MW started its commercial operation in 2005. However, in less than 2 years of its operation, the plant has indicated significant capacity degradation. Consequently, TNB carried few investigations to determine the cause for the capacity degradation. This paper describes the approach taken and the outcomes of the investigations.
TNB新投入使用的联合循环发电厂的性能退化研究-以波德申Tuanku Jaafar发电厂PD1为例
波德申Tuanku Jaafar发电站(PD1)一期工程是Tenaga国家电力公司(TNB)最新的发电厂之一。该联合循环电厂标称容量为750兆瓦,于2005年开始商业运行。然而,在运行不到2年的时间里,该工厂已经显示出明显的产能下降。因此,TNB很少进行调查以确定容量下降的原因。本文描述了所采取的方法和调查的结果。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信