Cost and fuel consumption in the Spanish electricity market: inefficiencies and risks with the present rules vs. an alternative bidding and clearing design

J. Revuelta, M. Pezic
{"title":"Cost and fuel consumption in the Spanish electricity market: inefficiencies and risks with the present rules vs. an alternative bidding and clearing design","authors":"J. Revuelta, M. Pezic","doi":"10.1109/EEM.2008.4579016","DOIUrl":null,"url":null,"abstract":"Besides allowing competition and security of supply, from the operational point of view an ideal electricity market should lead to a least cost generation program. That is, respecting all security and environmental criteria, there should be no lower cost way to cover the hourly demand. The Spanish bidding design for the spot market, responsible for the final generation program, is found inadequate to reach such goal, and to imply higher fuel consumption, cost and emissions, plus also certain risks for generation companies. Some inadequacies are identified, and an alternative bidding design is proposed, estimated to better achieve the mentioned objective. Using real and estimated data from the Spanish electric system, alternative generation programs were calculated for four representative weeks, and compared to the ones actually scheduled by the market, showing that savings of about 5.2% in cost of thermal generation and 3.9% in emissions are possible in the Spanish electric system.","PeriodicalId":118618,"journal":{"name":"2008 5th International Conference on the European Electricity Market","volume":"88 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-05-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 5th International Conference on the European Electricity Market","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/EEM.2008.4579016","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

Besides allowing competition and security of supply, from the operational point of view an ideal electricity market should lead to a least cost generation program. That is, respecting all security and environmental criteria, there should be no lower cost way to cover the hourly demand. The Spanish bidding design for the spot market, responsible for the final generation program, is found inadequate to reach such goal, and to imply higher fuel consumption, cost and emissions, plus also certain risks for generation companies. Some inadequacies are identified, and an alternative bidding design is proposed, estimated to better achieve the mentioned objective. Using real and estimated data from the Spanish electric system, alternative generation programs were calculated for four representative weeks, and compared to the ones actually scheduled by the market, showing that savings of about 5.2% in cost of thermal generation and 3.9% in emissions are possible in the Spanish electric system.
西班牙电力市场的成本和燃料消耗:现行规则的低效率和风险与替代投标和清算设计
除了允许竞争和供应安全之外,从运营的角度来看,理想的电力市场应该导致成本最低的发电计划。也就是说,在尊重所有安全和环境标准的情况下,不应该有更低的成本来满足每小时的需求。负责最终发电项目的西班牙现货市场招标设计不足以实现这一目标,并且意味着更高的燃料消耗、成本和排放,以及发电公司的一定风险。发现了一些不足之处,并提出了另一种投标设计,估计可以更好地实现上述目标。利用西班牙电力系统的真实和估计数据,计算了四个代表性周的替代发电计划,并与市场实际计划的替代发电计划进行了比较,结果表明,西班牙电力系统可以节省约5.2%的火力发电成本和3.9%的排放成本。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信