Feasibility Study of Public Health Center X

W. Tambunan, T. Pawitra, Riko Yehezkiel Siagian
{"title":"Feasibility Study of Public Health Center X","authors":"W. Tambunan, T. Pawitra, Riko Yehezkiel Siagian","doi":"10.32734/JSTI.V23I2.6391","DOIUrl":null,"url":null,"abstract":"Public Health Center X is the first level health facility service provider in subdistrict X. Established in 1975, UPT Puskesmas X has never conducted a feasibility study which has been regulated since 2014. Based on these problems, this study aims to conduct a feasibility study on a new building. Aspects contained in Permenkes No. 75 of 2014 namely aspects of location, buildings, facilities and infrastructure, health equipment, personnel, and organization. There is a health center design stage which is made in accordance with the criteria of the Minister of Health No. 75 of 2014. Based on the results of research conducted on the new building of Public Health Center X, it is known that the location aspect meets 87.5% of the location criteria, the building aspect meets 100% of the building suitability, the facilities and infrastructure aspect meets 100% of the eligibility criteria, the equipment aspect only meets 34% of the equipment that must be owned, the manpower aspect fulfills 73% of the total workforce owned, and the organizational aspect meets 100% of the conformity of the organizational structure, so that overall Public Health Center X has a feasibility percentage of 82.4%. Public Health Center X needs to evaluate and improve. Improvements were made to the location aspect, namely, parking facilities by increasing the capacity of the parking lot. Then do the procurement and purchase of medical equipment because there are still 66% of equipment that is lacking, as well as adding health workers to the positions of public health workers, environmental health workers, and workers.","PeriodicalId":221079,"journal":{"name":"Jurnal Sistem Teknik Industri","volume":"47 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-07-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Sistem Teknik Industri","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.32734/JSTI.V23I2.6391","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Public Health Center X is the first level health facility service provider in subdistrict X. Established in 1975, UPT Puskesmas X has never conducted a feasibility study which has been regulated since 2014. Based on these problems, this study aims to conduct a feasibility study on a new building. Aspects contained in Permenkes No. 75 of 2014 namely aspects of location, buildings, facilities and infrastructure, health equipment, personnel, and organization. There is a health center design stage which is made in accordance with the criteria of the Minister of Health No. 75 of 2014. Based on the results of research conducted on the new building of Public Health Center X, it is known that the location aspect meets 87.5% of the location criteria, the building aspect meets 100% of the building suitability, the facilities and infrastructure aspect meets 100% of the eligibility criteria, the equipment aspect only meets 34% of the equipment that must be owned, the manpower aspect fulfills 73% of the total workforce owned, and the organizational aspect meets 100% of the conformity of the organizational structure, so that overall Public Health Center X has a feasibility percentage of 82.4%. Public Health Center X needs to evaluate and improve. Improvements were made to the location aspect, namely, parking facilities by increasing the capacity of the parking lot. Then do the procurement and purchase of medical equipment because there are still 66% of equipment that is lacking, as well as adding health workers to the positions of public health workers, environmental health workers, and workers.
X公共卫生中心可行性研究
X公共卫生中心是X街道一级卫生设施服务提供商,成立于1975年,UPT Puskesmas X从未进行过可行性研究,自2014年以来一直受到监管。基于这些问题,本研究旨在对新建建筑进行可行性研究。2014年第75号Permenkes法令所载方面,即地点、建筑物、设施和基础设施、卫生设备、人员和组织方面。根据2014年第75号卫生部长的标准,有一个保健中心设计阶段。根据对公共卫生中心X新楼的研究结果,已知位置方面满足87.5%的位置标准,建筑方面满足100%的建筑适宜性,设施和基础设施方面满足100%的合格标准,设备方面只满足34%的必须拥有的设备,人力方面满足73%的总劳动力。组织方面100%符合组织结构的符合性,因此整体X公共卫生中心的可行性百分比为82.4%。公共卫生中心X需要评估和改进。在位置方面进行了改进,即通过增加停车场的容量来增加停车设施。然后是医疗设备的采购和购买,因为仍有66%的设备缺乏,以及增加卫生工作者到公共卫生工作者、环境卫生工作者和工人的岗位上。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信