Comparison of discharges measured from a generator's terminals and from an antenna in front of the slots

C. Hudon, W. Torres, M. Bélec, R. Contreras
{"title":"Comparison of discharges measured from a generator's terminals and from an antenna in front of the slots","authors":"C. Hudon, W. Torres, M. Bélec, R. Contreras","doi":"10.1109/EEIC.2001.965753","DOIUrl":null,"url":null,"abstract":"Partial discharge (PD) measurements have been carried out off-line from the terminals of two generators at the Guri Power plant. In addition, an antenna (developed by Tennessee Valley Authority (TVA)) was used to detect the electromagnetic signal in front of each slot of the two stator windings. The characteristic PRPD (phase resolved partial discharge) signature of internal discharges was detected both from line end measurements and in front of every slot. Other features characteristic of specific defects, such as slot discharges, was detected both from the terminal and from the TVA probe only for one of the generators. In contradistinction, for the other generator, slot discharges were only seen with the TVA/PRPD measurements and not from the terminals. The advantages and the limits of the measurements made from both the line end terminals and with the TVA probe are further discussed based on the results from the two generators.","PeriodicalId":228071,"journal":{"name":"Proceedings: Electrical Insulation Conference and Electrical Manufacturing and Coil Winding Conference (Cat. No.01CH37264)","volume":"11 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2001-10-16","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"17","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings: Electrical Insulation Conference and Electrical Manufacturing and Coil Winding Conference (Cat. No.01CH37264)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/EEIC.2001.965753","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 17

Abstract

Partial discharge (PD) measurements have been carried out off-line from the terminals of two generators at the Guri Power plant. In addition, an antenna (developed by Tennessee Valley Authority (TVA)) was used to detect the electromagnetic signal in front of each slot of the two stator windings. The characteristic PRPD (phase resolved partial discharge) signature of internal discharges was detected both from line end measurements and in front of every slot. Other features characteristic of specific defects, such as slot discharges, was detected both from the terminal and from the TVA probe only for one of the generators. In contradistinction, for the other generator, slot discharges were only seen with the TVA/PRPD measurements and not from the terminals. The advantages and the limits of the measurements made from both the line end terminals and with the TVA probe are further discussed based on the results from the two generators.
从发电机端子和槽前天线测量的放电比较
对古里电厂两台发电机的终端进行了局部放电(PD)的离线测量。此外,使用田纳西河谷管理局(TVA)开发的天线来检测两个定子绕组每个槽前的电磁信号。从线端测量和每个槽前检测到内部放电的特征PRPD(相位分解局部放电)特征。特定缺陷的其他特征,如槽放电,仅从其中一个发电机的终端和TVA探头检测到。相比之下,对于另一个发电机,槽放电只能通过TVA/PRPD测量看到,而不能从终端看到。根据两个发生器的测量结果,进一步讨论了用线路末端和用TVA探头测量的优点和局限性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信