Unfixing the fixed scope project: using agile methodologies to create flexibility in project scope

Jeff Patton
{"title":"Unfixing the fixed scope project: using agile methodologies to create flexibility in project scope","authors":"Jeff Patton","doi":"10.1109/ADC.2003.1231465","DOIUrl":null,"url":null,"abstract":"Although it seems to be common knowledge that it's impossible to succeed in a project with fixed time, quality and scope, we often continue to try anyway. This experience report discusses our successful failure at running fixed time and scope projects. We say successful failure because we actually failed to fix scope but arrived at an acceptable way to vary scope and deliver on time in an environment not normally amenable to variable scope. We discuss the methods used and make recommendations on how we might unfix scope in our development environment.","PeriodicalId":325418,"journal":{"name":"Proceedings of the Agile Development Conference, 2003. ADC 2003","volume":"18 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2003-06-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"9","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the Agile Development Conference, 2003. ADC 2003","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ADC.2003.1231465","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 9

Abstract

Although it seems to be common knowledge that it's impossible to succeed in a project with fixed time, quality and scope, we often continue to try anyway. This experience report discusses our successful failure at running fixed time and scope projects. We say successful failure because we actually failed to fix scope but arrived at an acceptable way to vary scope and deliver on time in an environment not normally amenable to variable scope. We discuss the methods used and make recommendations on how we might unfix scope in our development environment.
解除固定范围的项目:使用敏捷方法在项目范围中创建灵活性
虽然我们都知道在固定的时间、质量和范围内完成一个项目是不可能成功的,但我们还是会继续尝试。这份经验报告讨论了我们在运行固定时间和范围的项目时的成功失败。我们说成功的失败是因为我们实际上没能确定范围,但在一个通常不适合可变范围的环境中,我们找到了一种可接受的方式来改变范围并按时交付。我们将讨论所使用的方法,并就如何在开发环境中取消作用域提出建议。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信