{"title":"Research on Key Assembling Technology of Tube Bundle Assembly of Hualong-1 Type Steam Generator","authors":"Ye Wanbing, Liu Yuanbin, Chen Yaomao, Zhang Sanjun, Wang Aili","doi":"10.1115/icone29-92130","DOIUrl":null,"url":null,"abstract":"\n Fangchenggang Phase II nuclear power project adopts the third generation advanced nuclear power technology of Hualong-1. The steam generator tube bundle assembly of the project adopts HL1000 type, which was manufactured for the first time in China. The tube bundle assembly is composed of three parts: tubes, support assembly of straight section of tube bundle and anti-vibration bar assembly of U tube bend. The structure of tube bundle assembly is novel, involving several kinds of parts and components, high assembly accuracy requirements and strict assembly sequence. During manufacturing of the tube bundle assembly, key manufacturing technologies including the installation and alignment of 9 pieces of Lattice Grid Assembly (diamond shaped holes) and tubesheet holes, anti-sagging control of tube bend section, integrated connection of anti-vibration components and anti-offset of anti-vibration components were successfully in command. The development of HL1000 tube bundle components was successfully completed, the independent research and manufacturing of products was realized, and the blanks of this new reactor manufacturing technology in China was filled in. This paper summarizes and analyzes the key assembly technology of HL1000 tube bundle assembly, so as to provide experience for the design and manufacture of steam generators of other reactor.","PeriodicalId":317622,"journal":{"name":"Volume 10: Advanced Methods of Manufacturing for Nuclear Reactors and Components","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-08-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Volume 10: Advanced Methods of Manufacturing for Nuclear Reactors and Components","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/icone29-92130","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Fangchenggang Phase II nuclear power project adopts the third generation advanced nuclear power technology of Hualong-1. The steam generator tube bundle assembly of the project adopts HL1000 type, which was manufactured for the first time in China. The tube bundle assembly is composed of three parts: tubes, support assembly of straight section of tube bundle and anti-vibration bar assembly of U tube bend. The structure of tube bundle assembly is novel, involving several kinds of parts and components, high assembly accuracy requirements and strict assembly sequence. During manufacturing of the tube bundle assembly, key manufacturing technologies including the installation and alignment of 9 pieces of Lattice Grid Assembly (diamond shaped holes) and tubesheet holes, anti-sagging control of tube bend section, integrated connection of anti-vibration components and anti-offset of anti-vibration components were successfully in command. The development of HL1000 tube bundle components was successfully completed, the independent research and manufacturing of products was realized, and the blanks of this new reactor manufacturing technology in China was filled in. This paper summarizes and analyzes the key assembly technology of HL1000 tube bundle assembly, so as to provide experience for the design and manufacture of steam generators of other reactor.
华龙1型蒸汽发生器管束总成关键装配技术研究
防城港二期核电工程采用华龙一号第三代先进核电技术。本项目蒸汽发生器管束总成采用国内首次生产的HL1000型。管束组件由三部分组成:管束、管束直段支撑组件和U型管弯减振棒组件。管束装配结构新颖,涉及多种零部件,装配精度要求高,装配顺序严格。在管束组件制造过程中,成功掌握了9件格网组件(菱形孔)与管板孔的安装对中、管弯段防下垂控制、减振组件集成连接、减振组件防偏移等关键制造技术。成功完成HL1000管束组件的开发,实现了产品的自主研发和制造,填补了国内这一新型反应堆制造技术的空白。本文对HL1000管束组件的关键装配技术进行了总结和分析,为其他反应堆蒸汽发生器的设计和制造提供经验。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信