{"title":"Evaluation of mean and variance approximations in three point estimation of task completion times using the beta and the Kumaraswamy distribution","authors":"Pablo Ortiz Bochard, Thomas Schwarz","doi":"10.1504/ijitm.2019.10024390","DOIUrl":null,"url":null,"abstract":"Estimation of task and project completion times within IT projects remains one of the most error-prone, but also most critical duties of an IT project manager. Various three-point methods of PERT have been evaluated by assuming that the true distribution is a beta-distribution. We evaluate PERT methods by comparing additionally with the Kumaraswamy distribution, which has an equal claim to be the true a-priori distribution for project completion times. We use skew and kurtosis in order to define test sets instead of simply choosing a range of shape parameters. We validate various approximations proposed in the literature and show that valid approximations are possible.","PeriodicalId":340536,"journal":{"name":"Int. J. Inf. Technol. Manag.","volume":"15 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Int. J. Inf. Technol. Manag.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1504/ijitm.2019.10024390","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Estimation of task and project completion times within IT projects remains one of the most error-prone, but also most critical duties of an IT project manager. Various three-point methods of PERT have been evaluated by assuming that the true distribution is a beta-distribution. We evaluate PERT methods by comparing additionally with the Kumaraswamy distribution, which has an equal claim to be the true a-priori distribution for project completion times. We use skew and kurtosis in order to define test sets instead of simply choosing a range of shape parameters. We validate various approximations proposed in the literature and show that valid approximations are possible.