Load flow study and conceptual system design of SEPTA's regional rail division traction power system

T. Kneschke, J.P. Hong, W. Naqvi
{"title":"Load flow study and conceptual system design of SEPTA's regional rail division traction power system","authors":"T. Kneschke, J.P. Hong, W. Naqvi","doi":"10.1109/RRCON.1994.289017","DOIUrl":null,"url":null,"abstract":"The purpose of this study was to develop a configuration of the modernized traction power supply system formerly owned by the Reading Railroad and recommend the most appropriate method for implementation of the proposed system. Load flow studies were performed to evaluate the system performance taking into account projected traffic density. Based on these studies, conceptual system design was performed which included development of procurement specifications for modern switchgear to be used in Wayne Junction and all autotransformer substations. In order to help realize the system modernization, an implementation plan spanning 12 years has been prepared. The plan identified issues to be resolved so that system modernization may proceed and included criteria for executing the system upgrade. Based on those criteria it was concluded that the system modernization should be performed with the following priorities: (1) the Wayne Junction substation modernization should be completed as soon as possible; (2) all existing autotransformer substations should be replaced; and (3) design and installation of additional static frequency converters will be required as the traffic approaches the projected density and the planned electrification extensions are realized. In order to help SEPTA with planning of the modernization program, budgetary construction costs for the new facilities were estimated. Combining the cost estimates and the 12-year implementation schedule, cash flow analyses were developed for present dollars and for dollars escalated to mid-point of construction of each facility.<<ETX>>","PeriodicalId":145407,"journal":{"name":"Proceedings of IEEE/ASME Joint Railroad Conference","volume":"33 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1994-03-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of IEEE/ASME Joint Railroad Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/RRCON.1994.289017","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 4

Abstract

The purpose of this study was to develop a configuration of the modernized traction power supply system formerly owned by the Reading Railroad and recommend the most appropriate method for implementation of the proposed system. Load flow studies were performed to evaluate the system performance taking into account projected traffic density. Based on these studies, conceptual system design was performed which included development of procurement specifications for modern switchgear to be used in Wayne Junction and all autotransformer substations. In order to help realize the system modernization, an implementation plan spanning 12 years has been prepared. The plan identified issues to be resolved so that system modernization may proceed and included criteria for executing the system upgrade. Based on those criteria it was concluded that the system modernization should be performed with the following priorities: (1) the Wayne Junction substation modernization should be completed as soon as possible; (2) all existing autotransformer substations should be replaced; and (3) design and installation of additional static frequency converters will be required as the traffic approaches the projected density and the planned electrification extensions are realized. In order to help SEPTA with planning of the modernization program, budgetary construction costs for the new facilities were estimated. Combining the cost estimates and the 12-year implementation schedule, cash flow analyses were developed for present dollars and for dollars escalated to mid-point of construction of each facility.<>
SEPTA区域轨道分区牵引电力系统的潮流研究与概念系统设计
本研究的目的是开发一个现代化的牵引供电系统,原雷丁铁路拥有的配置,并建议最合适的方法来实施拟议的系统。考虑到预计的交通密度,进行负荷流研究以评估系统性能。基于这些研究,进行了概念系统设计,其中包括为Wayne Junction和所有自变变电站使用的现代开关柜制定采购规范。为实现制度现代化,制定了为期12年的实施计划。该计划确定了要解决的问题,以便系统现代化可以进行,并包括执行系统升级的标准。根据这些标准,得出结论,系统现代化应按以下优先顺序进行:(1)尽快完成Wayne Junction变电站的现代化;(2)全部更换现有自变变电站;(3)随着交通接近预计密度和计划的电气化扩展的实现,将需要设计和安装额外的静态变频器。为了帮助SEPTA规划现代化项目,对新设施的预算建设成本进行了估算。结合成本估算和12年的实施时间表,对当前美元和每个设施建设中期的美元进行了现金流量分析
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信