INVESTMENT RISK EVALUATION OF SIIRT MADENKÖY COPPER MINE IN TURKEY

Merve Karaabat Varol, I. Ugur, S. G. Erçelebi
{"title":"INVESTMENT RISK EVALUATION OF SIIRT MADENKÖY COPPER MINE IN TURKEY","authors":"Merve Karaabat Varol, I. Ugur, S. G. Erçelebi","doi":"10.30516/BILGESCI.487621","DOIUrl":null,"url":null,"abstract":"Mining investments are high-risky investments due to mineral deposit uncertainties. Therefore, before any investment decision is given, an economic assessment should be performed and several risk situations must be taken into consideration. In this study, it was examined whether or not an investment made in a copper mine in Siirt, Turkey is economical by using Sensitivity Analysis and Monte Carlo Simulation. The aim of this study is to construct cash flows for this copper mine with an average grade of 2.35% Cu and 39.821.000 tons reserve throughout 25 years for two different situations. In the first case, it was assumed that the total investment amount will be covered by 100% equity, while in the second case the total investment amount was assumed to be 30% equity and 70% bank loan. In the Sensitivity Analysis, mineral processing and operating costs, the average grades and ore concentrate sale prices were evaluated over optimistic and pessimistic forecasts. Changes in the net present value and internal rate of return were examined without risk. Monte Carlo Simulation was run by using computer software program @Risk 6.0 and applied to investment criteria for this copper mine field. The analysis of the output modelling situations where decisions were made under uncertainty gave reliable results by quantifying the degree of risk for this mining project. Consequently, if the investment was provided with 100% equity, NPV was 136.369.150,7 $ and IRR was 32% with a discount rate of 15%, probably as likely to harm the project was about 0,018. If the investment was provided with 30% equity, NPV was 111.742.245,4 $, IRR was 28% with a discount rate of 15%, probably as likely to harm the project was about 0,05. In accordance with the results, the investment can be said to be a profitable project in both assumptions.","PeriodicalId":133012,"journal":{"name":"Bilge International Journal of Science and Technology Research","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-03-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"7","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bilge International Journal of Science and Technology Research","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30516/BILGESCI.487621","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 7

Abstract

Mining investments are high-risky investments due to mineral deposit uncertainties. Therefore, before any investment decision is given, an economic assessment should be performed and several risk situations must be taken into consideration. In this study, it was examined whether or not an investment made in a copper mine in Siirt, Turkey is economical by using Sensitivity Analysis and Monte Carlo Simulation. The aim of this study is to construct cash flows for this copper mine with an average grade of 2.35% Cu and 39.821.000 tons reserve throughout 25 years for two different situations. In the first case, it was assumed that the total investment amount will be covered by 100% equity, while in the second case the total investment amount was assumed to be 30% equity and 70% bank loan. In the Sensitivity Analysis, mineral processing and operating costs, the average grades and ore concentrate sale prices were evaluated over optimistic and pessimistic forecasts. Changes in the net present value and internal rate of return were examined without risk. Monte Carlo Simulation was run by using computer software program @Risk 6.0 and applied to investment criteria for this copper mine field. The analysis of the output modelling situations where decisions were made under uncertainty gave reliable results by quantifying the degree of risk for this mining project. Consequently, if the investment was provided with 100% equity, NPV was 136.369.150,7 $ and IRR was 32% with a discount rate of 15%, probably as likely to harm the project was about 0,018. If the investment was provided with 30% equity, NPV was 111.742.245,4 $, IRR was 28% with a discount rate of 15%, probably as likely to harm the project was about 0,05. In accordance with the results, the investment can be said to be a profitable project in both assumptions.
土耳其siirt madenkÖy铜矿投资风险评价
由于矿藏的不确定性,矿业投资属于高风险投资。因此,在作出任何投资决定之前,应进行经济评估,并必须考虑到几种风险情况。在本研究中,通过灵敏度分析和蒙特卡罗模拟,研究了土耳其锡尔特铜矿的投资是否经济。本研究的目的是为该铜品位平均为2.35%,储量为3982.1万吨的铜矿构建两种不同情况下25年的现金流。在第一种情况下,假设总投资金额将由100%的股权覆盖,而在第二种情况下,总投资金额假设为30%的股权和70%的银行贷款。在敏感性分析中,对选矿和运营成本、平均品位和精矿销售价格进行了乐观和悲观预测。净现值和内部收益率的变化是无风险的。利用计算机软件@Risk 6.0进行蒙特卡罗模拟,并将其应用于该铜矿田的投资准则。对在不确定情况下作出决策的产出模型情况的分析,通过量化该采矿项目的风险程度,得出了可靠的结果。因此,如果投资为100%股权,NPV为136.369.150,7美元,IRR为32%,贴现率为15%,可能对项目造成的损害约为0,018。如果投资以30%的股权提供,NPV为111.742.245,4美元,IRR为28%,贴现率为15%,可能对项目造成的损害约为0.05。根据结果,在两种假设下,该投资可以说是一个有利可图的项目。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信