Oversight and Efficiency in Public Projects: A Regression Discontinuity Analysis

E. Calvo, Ruomeng Cui, J. C. Serpa
{"title":"Oversight and Efficiency in Public Projects: A Regression Discontinuity Analysis","authors":"E. Calvo, Ruomeng Cui, J. C. Serpa","doi":"10.2139/ssrn.2876840","DOIUrl":null,"url":null,"abstract":"During the execution of a public project (e.g., the construction of a hospital), should regulators continually scrutinize the contractor’s operations? Or is this behavior obstructive? In this paper we explore the causal impact of government oversight on a project’s delay time and cost overrun. To this end, we collect a sample of 30,004 projects across 70 U.S. federal agencies and 5,557 private contractors. We exploit a regulatory bylaw in federal procurement. If a project’s estimated budget exceeds a pre-established cutoff, then the project’s operations are heavily scrutinized through evaluation teams, progress reports, and expenditure approval forms. If, conversely, a project’s budget is below this cutoff, these operational checks are waived. Using a regression discontinuity design, we find that decreasing the intensity of oversight significantly decreases a project’s delay time and cost overrun. Further, our results indicate that the effectiveness of government oversight depends on (i) the contract type and (ii) the contractor’s experience.","PeriodicalId":330590,"journal":{"name":"ERN: Procurement (Topic)","volume":"33 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"37","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ERN: Procurement (Topic)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2139/ssrn.2876840","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 37

Abstract

During the execution of a public project (e.g., the construction of a hospital), should regulators continually scrutinize the contractor’s operations? Or is this behavior obstructive? In this paper we explore the causal impact of government oversight on a project’s delay time and cost overrun. To this end, we collect a sample of 30,004 projects across 70 U.S. federal agencies and 5,557 private contractors. We exploit a regulatory bylaw in federal procurement. If a project’s estimated budget exceeds a pre-established cutoff, then the project’s operations are heavily scrutinized through evaluation teams, progress reports, and expenditure approval forms. If, conversely, a project’s budget is below this cutoff, these operational checks are waived. Using a regression discontinuity design, we find that decreasing the intensity of oversight significantly decreases a project’s delay time and cost overrun. Further, our results indicate that the effectiveness of government oversight depends on (i) the contract type and (ii) the contractor’s experience.
公共项目的监督与效率:一个回归不连续分析
在公共项目的执行过程中(例如,医院的建设),监管机构是否应该持续审查承包商的运作?或者这种行为是阻碍性的?本文探讨了政府监管对项目延误时间和成本超支的因果影响。为此,我们收集了70个美国联邦机构和5,557个私人承包商的30,000个项目样本。我们利用了联邦采购的规章制度。如果一个项目的估计预算超过了预先设定的截止日期,那么项目的运作将通过评估小组、进度报告和支出批准表格进行严格审查。相反,如果一个项目的预算低于这个截止值,这些操作检查将被放弃。使用回归不连续设计,我们发现降低监督强度可以显著降低项目的延迟时间和成本超支。此外,我们的研究结果表明,政府监督的有效性取决于(i)合同类型和(ii)承包商的经验。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信