Lessons Learned in Horizontal Well Workovers and Sand Cleanouts, in Cerro Negro Field, Venezuela

Lenin Perdomo, Giancarlo Molina, Francisco J Mavares, Marian Limpio, Elio Correa, M. Anez
{"title":"Lessons Learned in Horizontal Well Workovers and Sand Cleanouts, in Cerro Negro Field, Venezuela","authors":"Lenin Perdomo, Giancarlo Molina, Francisco J Mavares, Marian Limpio, Elio Correa, M. Anez","doi":"10.2118/209801-pa","DOIUrl":null,"url":null,"abstract":"\n The Orinoco Oil Belt in Venezuela contains the largest known deposits of heavy oil in the world, and Cerro Negro is part of the fields in this area. However, the sand production is a major issue which affects the oil production in this field. There are some major issues that stand in the way of the proper cleanout of these wells. These problems include low reservoir pressure, geometry of the wells, and extremely high oil viscosity. Another major problem is the presence of big pieces of progressing cavity pumps (PCP) elastomers, some metallic parts from pressure and temperature sensors configuration, and other metallic parts from previous workover rig operations, encountered during cleanout operations. As a result of these difficulties, some of the past jobs performed in this field were unsuccessful.\n After these unssuccessful jobs, a campaign of recent multiple sand cleanout jobs was planned in the Cerro Negro field. Numerous difficulties arose during these jobs. These issues were largely due to the presence of big pieces of PCP elastomers and metallic parts. An additional issue was the low reservoir pressure. Due to the size of the casing/liner and the horizontal section, the annulus fluid velocity obtained was insufficient. Therefore, several techniques were applied to overcome these problems. One of these methods was to use reverse circulation for the sand cleanout in the 9-5/8-in. slanted casing section, while circulation was still possible to obtain a higher fluid velocity. Afterward, once the circulation was lost, a special stroking pump was used alongside a large string of tubing to store large amounts of sand and debris. This tool was also used to recover pieces of PCP elastomers and other metallic parts. This tool uses a piston pump to create a vacuum effect, and fluid circulation is not needed for the cleanout. Without this innovative stroking pump, it would have been almost impossible to recover these large pieces. This was the first time this innovative tool was used in these types of wells. When the open horizontal 7-in. production zone was reached, coiled tubing (CT) was used with the proper proportion of diesel and nitrogen to obtain enough fluid velocity and the proper equivalent density.\n In the end, when necessary, a smaller reliner was run depending on the information obtained during the analysis of the grain sizes. Some techniques were applied to run the reliner successfully in an old and worn out casing, where the geometry of the well and high doglegs caused difficulties.\n The challenges to complete the cleanout of the well with lost circulation problems included a large annulus area in the highly slanted and horizontal sections, the extremely high oil viscosity, and the presence of large pieces of PCP and metallic parts. These challenges were overcome by using different methods such as the special stroking pump, reverse circulation in the 9.625-in. section, and CT with the proper diesel and nitrogen proportions. Additionally, to keep sand production under control in the cleaned wells, a smaller reliner was run.\n Finally, these workover jobs were finalized to bring these wells back into production successfully. The oil production results of these operations are shown in this paper, and demonstrated that it is possible to retrieve the production in the sanded wells of the Orinoco Belt in a profitable way.","PeriodicalId":153181,"journal":{"name":"SPE Production & Operations","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-04-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"SPE Production & Operations","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/209801-pa","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

The Orinoco Oil Belt in Venezuela contains the largest known deposits of heavy oil in the world, and Cerro Negro is part of the fields in this area. However, the sand production is a major issue which affects the oil production in this field. There are some major issues that stand in the way of the proper cleanout of these wells. These problems include low reservoir pressure, geometry of the wells, and extremely high oil viscosity. Another major problem is the presence of big pieces of progressing cavity pumps (PCP) elastomers, some metallic parts from pressure and temperature sensors configuration, and other metallic parts from previous workover rig operations, encountered during cleanout operations. As a result of these difficulties, some of the past jobs performed in this field were unsuccessful. After these unssuccessful jobs, a campaign of recent multiple sand cleanout jobs was planned in the Cerro Negro field. Numerous difficulties arose during these jobs. These issues were largely due to the presence of big pieces of PCP elastomers and metallic parts. An additional issue was the low reservoir pressure. Due to the size of the casing/liner and the horizontal section, the annulus fluid velocity obtained was insufficient. Therefore, several techniques were applied to overcome these problems. One of these methods was to use reverse circulation for the sand cleanout in the 9-5/8-in. slanted casing section, while circulation was still possible to obtain a higher fluid velocity. Afterward, once the circulation was lost, a special stroking pump was used alongside a large string of tubing to store large amounts of sand and debris. This tool was also used to recover pieces of PCP elastomers and other metallic parts. This tool uses a piston pump to create a vacuum effect, and fluid circulation is not needed for the cleanout. Without this innovative stroking pump, it would have been almost impossible to recover these large pieces. This was the first time this innovative tool was used in these types of wells. When the open horizontal 7-in. production zone was reached, coiled tubing (CT) was used with the proper proportion of diesel and nitrogen to obtain enough fluid velocity and the proper equivalent density. In the end, when necessary, a smaller reliner was run depending on the information obtained during the analysis of the grain sizes. Some techniques were applied to run the reliner successfully in an old and worn out casing, where the geometry of the well and high doglegs caused difficulties. The challenges to complete the cleanout of the well with lost circulation problems included a large annulus area in the highly slanted and horizontal sections, the extremely high oil viscosity, and the presence of large pieces of PCP and metallic parts. These challenges were overcome by using different methods such as the special stroking pump, reverse circulation in the 9.625-in. section, and CT with the proper diesel and nitrogen proportions. Additionally, to keep sand production under control in the cleaned wells, a smaller reliner was run. Finally, these workover jobs were finalized to bring these wells back into production successfully. The oil production results of these operations are shown in this paper, and demonstrated that it is possible to retrieve the production in the sanded wells of the Orinoco Belt in a profitable way.
委内瑞拉Cerro Negro油田水平井修井和清砂经验教训
委内瑞拉的奥里诺科石油带拥有世界上已知最大的重油矿床,而塞罗内格罗是该地区油田的一部分。然而,出砂是影响该油田产量的主要问题。在对这些井进行适当的清洗时,存在一些主要问题。这些问题包括储层压力低、井的几何形状和极高的油粘度。另一个主要问题是,在洗井作业中会遇到大块的螺杆泵(PCP)弹性体、压力和温度传感器配置中的一些金属部件,以及之前修井机作业中的其他金属部件。由于这些困难,过去在该领域进行的一些工作是不成功的。在这些不成功的作业之后,最近在Cerro Negro油田计划进行多次清砂作业。在这些工作中出现了许多困难。这些问题主要是由于存在大块的PCP弹性体和金属部件。另一个问题是储层压力低。由于套管/尾管尺寸和水平段的原因,所获得的环空流体速度不足。因此,采用了几种技术来克服这些问题。其中一种方法是在9-5/8-in井段使用反循环进行清砂。斜套管段,同时循环仍有可能获得更高的流体速度。之后,一旦失去循环,就会使用一个特殊的冲程泵和一长串油管来储存大量的沙子和碎屑。该工具还用于回收PCP弹性体和其他金属部件。该工具使用柱塞泵产生真空效果,清洗时不需要流体循环。如果没有这种创新的冲程泵,几乎不可能回收这些大碎片。这是该创新工具首次在此类井中使用。当开启水平7寸时。在达到生产区域后,使用连续油管(CT)配合适当比例的柴油和氮气,以获得足够的流体速度和适当的当量密度。最后,在必要时,根据在粒度分析中获得的信息,运行较小的减速器。在老旧磨损的套管中,由于井的几何形状和高狗腿造成了困难,应用了一些技术成功下入了尾管。存在漏失问题的井的清洗面临的挑战包括:大斜度和水平段的大环空面积,极高的油粘度,以及存在大块的PCP和金属部件。通过使用不同的方法克服了这些挑战,例如特殊冲程泵,9.625-in的反向循环。用适当比例的柴油和氮气进行CT处理。此外,为了控制清洗井的出砂,下入了一个较小的尾管。最后,这些修井作业完成,使这些井成功恢复生产。本文给出了这些作业的采油效果,并证明了在奥里诺科带砂井中采油是可以盈利的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信