Kajian Teknis Geometri Jalan Tambang untuk Mengurangi Dampak Slippery sebagai Upaya Meningkatkan Produksi Nikel PT ANTAM (Persero) Tbk di Kecamatan Maba, Kabupaten Halmahera Timur, Provinsi Maluku Utara
{"title":"Kajian Teknis Geometri Jalan Tambang untuk Mengurangi Dampak Slippery sebagai Upaya Meningkatkan Produksi Nikel PT ANTAM (Persero) Tbk di Kecamatan Maba, Kabupaten Halmahera Timur, Provinsi Maluku Utara","authors":"Sandy Herdiansyah, Zaenal, Iswandaru","doi":"10.29313/bcsme.v2i2.4018","DOIUrl":null,"url":null,"abstract":"Abstract. PT Aneka Tambang Tbk nickel production located in Wayafli Village, Maba District, East Halmahera Regency, North Maluku Province, to support the mining process, the Tanjung Buli site uses a conveyance with the type of Articulated Dump Truck CAT 745 and Volvo FMX 440 8X4 with a Volvo EC480EL loading and unloading tool, one of the obstacles at the Tanjung Buli site is the geometry of the road and the duration of slippery This research aims to be able to find out the condition of the transport road and activities slippery handling, Based on research, the condition of the road geometry which includes the actual road width condition of the straight condition has the smallest width of 5,944 - 20,329 meters with the condition of the bend road has a size of 6.201- 30.714 meters, with the highest grade being 19% for the actual superelevation of a maximum of 7.2%, the standard grade used is 12% and after calculations, the minimum superelevation value is 6% Based on the productivity of the support tool for support tools for support tools The CAT D6RXL bulldozer is 147.40 m3/h and the Komatsu D85ESS-2A is 189.27 m3/h. The total slippery handling duration in the pre-production area of 72.51 minutes can be reduced by repairing the transport road, especially in the crossfall section to be able to drain rainwater so that there is no inundation, it can reduce the duration of 44.61 minutes, then by adding a bulldozer unit the duration can be reduced to 29.74 minutes and changing the pushing method to side by side dozing to 29.45 minutes. \nAbstrak. PT Aneka Tambang Tbk produksi nikel yang terletak di Desa Wayafli Kecamatan Maba Kabupaten Halmahera Timur Provinsi Maluku Utara, untuk menunjang proses penambangan, site Tanjung Buli menggunakan alat angkut dengan jenis Articulated Dump Truck CAT 745 dan Volvo FMX 440 8X4 dengan alat gali muat Volvo EC480EL salah satu hambatan yang ada pada site Tanjung Buli adalah geometri jalan serta durasi slippery Penelitian ini memiliki tujuan untuk dapat mengetahui kondisi jalan angkut dan kegiatan penanganan slippery, Berdasarkan penelitian, kondisi dari geometri jalan yang termasuk kondisi lebar jalan aktual kondisi lurus memiliki lebar terkecil 5,944 - 20,329 meter dengan kondisi jalan tikungan memiliki ukuran 6,201- 30,714 meter, dengan grade tertinggi adalah 19% untuk superelevasi actual maksimal 7,2%, standart grade yang digunakan adalah 12% dan setelah dilakukan perhitungan, nilai superelevasi minimum adalah 6% Berdasarkan produktivitas dari alat support untuk alat support Bulldozer CAT D6RXL sebesar 147,40 m3/jam dan Komatsu D85ESS-2A sebesar 189,27 m3/jam. Durasi penanganan slippery total pada areal pra-produksi sebesar 72,51 menit dapat dikurangi dengan cara memperbaiki jalan angkut terutama pada bagian crossfall untuk dapat mengalirkan air hujan agar tidak terjadi genangan dapat mengurangi durasi 44,61 menit, lalu dengan menambah unit bulldozer durasi dapat berkurang menjadi 29,74 menit dan mengganti metode pendorongan menjadi side by side dozing menjadi 29,45 menit.","PeriodicalId":187584,"journal":{"name":"Bandung Conference Series: Mining Engineering","volume":"19 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Bandung Conference Series: Mining Engineering","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.29313/bcsme.v2i2.4018","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
Abstract. PT Aneka Tambang Tbk nickel production located in Wayafli Village, Maba District, East Halmahera Regency, North Maluku Province, to support the mining process, the Tanjung Buli site uses a conveyance with the type of Articulated Dump Truck CAT 745 and Volvo FMX 440 8X4 with a Volvo EC480EL loading and unloading tool, one of the obstacles at the Tanjung Buli site is the geometry of the road and the duration of slippery This research aims to be able to find out the condition of the transport road and activities slippery handling, Based on research, the condition of the road geometry which includes the actual road width condition of the straight condition has the smallest width of 5,944 - 20,329 meters with the condition of the bend road has a size of 6.201- 30.714 meters, with the highest grade being 19% for the actual superelevation of a maximum of 7.2%, the standard grade used is 12% and after calculations, the minimum superelevation value is 6% Based on the productivity of the support tool for support tools for support tools The CAT D6RXL bulldozer is 147.40 m3/h and the Komatsu D85ESS-2A is 189.27 m3/h. The total slippery handling duration in the pre-production area of 72.51 minutes can be reduced by repairing the transport road, especially in the crossfall section to be able to drain rainwater so that there is no inundation, it can reduce the duration of 44.61 minutes, then by adding a bulldozer unit the duration can be reduced to 29.74 minutes and changing the pushing method to side by side dozing to 29.45 minutes.
Abstrak. PT Aneka Tambang Tbk produksi nikel yang terletak di Desa Wayafli Kecamatan Maba Kabupaten Halmahera Timur Provinsi Maluku Utara, untuk menunjang proses penambangan, site Tanjung Buli menggunakan alat angkut dengan jenis Articulated Dump Truck CAT 745 dan Volvo FMX 440 8X4 dengan alat gali muat Volvo EC480EL salah satu hambatan yang ada pada site Tanjung Buli adalah geometri jalan serta durasi slippery Penelitian ini memiliki tujuan untuk dapat mengetahui kondisi jalan angkut dan kegiatan penanganan slippery, Berdasarkan penelitian, kondisi dari geometri jalan yang termasuk kondisi lebar jalan aktual kondisi lurus memiliki lebar terkecil 5,944 - 20,329 meter dengan kondisi jalan tikungan memiliki ukuran 6,201- 30,714 meter, dengan grade tertinggi adalah 19% untuk superelevasi actual maksimal 7,2%, standart grade yang digunakan adalah 12% dan setelah dilakukan perhitungan, nilai superelevasi minimum adalah 6% Berdasarkan produktivitas dari alat support untuk alat support Bulldozer CAT D6RXL sebesar 147,40 m3/jam dan Komatsu D85ESS-2A sebesar 189,27 m3/jam. Durasi penanganan slippery total pada areal pra-produksi sebesar 72,51 menit dapat dikurangi dengan cara memperbaiki jalan angkut terutama pada bagian crossfall untuk dapat mengalirkan air hujan agar tidak terjadi genangan dapat mengurangi durasi 44,61 menit, lalu dengan menambah unit bulldozer durasi dapat berkurang menjadi 29,74 menit dan mengganti metode pendorongan menjadi side by side dozing menjadi 29,45 menit.
抽象的。PT Aneka Tambang Tbk镍生产位于北马鲁古省East Halmahera Regency Maba区的Wayafli村,为了支持采矿过程,Tanjung Buli现场使用了铰接式自卸卡车CAT 745和沃尔沃FMX 440 8X4的运输工具,并配有沃尔沃EC480EL装卸工具。的障碍之一在海岬Buli网站是道路的几何和湿滑的持续时间这个研究的目的是能够找出交通道路的状况和活动滑处理,基于研究、道路几何的状况,包括连续的实际道路宽度条件条件的最小宽度5944 - 20329米的条件弯曲道路的大小为6.201 - 30.714米,实际超标高不超过7.2%,最高标高为19%,采用标准标高12%,经计算,最小超标高值为6%。根据支护工具的支护工具的支护工具的生产率,CAT D6RXL推土机为147.40 m3/h,小松d85ss - 2a为189.27 m3/h。预生产区湿滑处理总时间为72.51分钟,通过对运输道路进行修复,特别是对横断面进行排水,使其不发生淹水,可减少时间44.61分钟,再增加一台推土机,可减少时间29.74分钟,将推挤方式改为并排打滑,减少时间29.45分钟。Abstrak。PT Aneka Tambang Tbk产品是nikksi yang terletak di Desa Wayafli Kecamatan Maba Kabupaten Halmahera Timur省Maluku Utara, untuk menunjang propropenambangan,网站丹戎布里蒙古纳坎alat angkut dengan jenis铰接式自卸卡车CAT 745 dan Volvo FMX 440 8X4 dengan alat gali muat Volvo EC480EL salah satu hambatan yang ada ada ada网站丹戎布里adalah geometri jalan serta durasi滑,Penelitian ini memiliki tujuan untuk dapat mengetahui kondisi jalan angkut dankegiatan penangananan滑,Berdasarkan PenelitianKondisi dari geometri jalan Yang termasuk Kondisi lebar jalan aktual Kondisi lurus memiliki lebar terkecil 5,944 - 20,329米登干Kondisi jalan tikungan memiliki ukuran 6,201- 30,714米登干等级tertinggi adalah 19% untuk superelevasi实际maksimal 7,2%,标准等级Yang digunakan adalah 12% Dan setelah dilakukan perhitungan,nilai superelevasi minimum adalah 6% Berdasarkan生产活动,D6RXL推土机147,40 m3/jam小松D85ESS-2A推土机189,27 m3/jamDurasi penanganan总帕达面积pra-produksi sebesar 72,51 menit dapat dikurangi dengan cara成员perbaiki jalan angkut terutama帕达巴吉crossfall untuk dapat mengalirkan air hujan agar tiak terjadi genangan dapat mengurangi Durasi推土机Durasi dapat berkurang menjadi 29,74 menit dan mengganti medodoronan menjadi并排打盹menjadi 29,45 menit。