{"title":"Minimization of Bottleneck and Workstations for Assembly Line Balancing Problem in Power Transformer Manufacturing Using Heuristics","authors":"N. A. Bakar, M. Ramli, M. Z. Zakaria, T. C. Sin, H. Masran","doi":"10.1109/ICSIMA.2018.8688780","DOIUrl":null,"url":null,"abstract":"This project deals with a case study of SALBP in power transformer manufacturing. Some workstations in assembly line experienced bottlenecks, while the others suffered with high idle time. Therefore, four heuristic methods are chosen in order to provide solutions for minimizing number of workstations and improve the bottlenecks simultaneously. In this study, LCR, RPW and LPT are successfully minimized number of workstation from 19 to 16 workstations. Consequently, these solutions affect the layout. On the contrary, SPT able to improve the bottleneck by reducing number of workstations from 19 to 17 without affect the line layout. Therefore, this has created an option for engineer to decide which decision should be implement to the assembly line due to enhance the line efficiency.","PeriodicalId":222751,"journal":{"name":"2018 IEEE 5th International Conference on Smart Instrumentation, Measurement and Application (ICSIMA)","volume":"7 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2018 IEEE 5th International Conference on Smart Instrumentation, Measurement and Application (ICSIMA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICSIMA.2018.8688780","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

Abstract

This project deals with a case study of SALBP in power transformer manufacturing. Some workstations in assembly line experienced bottlenecks, while the others suffered with high idle time. Therefore, four heuristic methods are chosen in order to provide solutions for minimizing number of workstations and improve the bottlenecks simultaneously. In this study, LCR, RPW and LPT are successfully minimized number of workstation from 19 to 16 workstations. Consequently, these solutions affect the layout. On the contrary, SPT able to improve the bottleneck by reducing number of workstations from 19 to 17 without affect the line layout. Therefore, this has created an option for engineer to decide which decision should be implement to the assembly line due to enhance the line efficiency.
用启发式方法求解电力变压器制造中装配线平衡问题的瓶颈和工作站最小化
本项目以SALBP在电力变压器制造中的应用为例进行了研究。装配线中的一些工作站遇到瓶颈,而另一些工作站则存在高空闲时间。因此,选择了四种启发式方法,以提供最小化工作站数量和同时改善瓶颈的解决方案。在本研究中,LCR、RPW和LPT成功地将工作站数量从19个减少到16个。因此,这些解决方案会影响布局。相反,SPT能够通过将工作站数量从19个减少到17个而不影响线路布局来改善瓶颈。因此,这为工程师提供了一个选择,以决定应该在装配线上实施哪些决策,以提高生产线效率。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信