Lúcio Ribeiro, C. Gusmão, Wilmar Feijo, Vicente Bezerra
{"title":"A case study for the implementation of an agile risk management process in multiple projects environments","authors":"Lúcio Ribeiro, C. Gusmão, Wilmar Feijo, Vicente Bezerra","doi":"10.1109/PICMET.2009.5262002","DOIUrl":null,"url":null,"abstract":"In Software Engineering, the software development is subject to several uncertainties that need to be managed so that they do not interfere with the defined project goals. In this context, agile methods have emerged as an alternative that can bring better results for certain types of project. Technical reports show that the number of successful projects is lower than desired. One of the possible reasons is that there are many companies do not apply Risk Management or apply it improperly. In some companies, it is possible that there is a need to lead the Project Risk Management focused on organizational environment, namely the relationship of these risks with several existing projects. In this light, the article's goal is to report the case study's experience for the implementation of an Agile Risk Management Process in multiple projects environments, called GARA (Gestão ágil de Riscos de Ambiente). Some projects were selected to participate in the process which aims to perform an active management of existing impediments mainly those affect more than one project because of its importance or being share resources among these projects. Benefits like the communication among Project Leaders and their experiences in solving impediments are also discussed.","PeriodicalId":185147,"journal":{"name":"PICMET '09 - 2009 Portland International Conference on Management of Engineering & Technology","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2009-09-25","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"PICMET '09 - 2009 Portland International Conference on Management of Engineering & Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PICMET.2009.5262002","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3
Abstract
In Software Engineering, the software development is subject to several uncertainties that need to be managed so that they do not interfere with the defined project goals. In this context, agile methods have emerged as an alternative that can bring better results for certain types of project. Technical reports show that the number of successful projects is lower than desired. One of the possible reasons is that there are many companies do not apply Risk Management or apply it improperly. In some companies, it is possible that there is a need to lead the Project Risk Management focused on organizational environment, namely the relationship of these risks with several existing projects. In this light, the article's goal is to report the case study's experience for the implementation of an Agile Risk Management Process in multiple projects environments, called GARA (Gestão ágil de Riscos de Ambiente). Some projects were selected to participate in the process which aims to perform an active management of existing impediments mainly those affect more than one project because of its importance or being share resources among these projects. Benefits like the communication among Project Leaders and their experiences in solving impediments are also discussed.
在软件工程中,软件开发受到几个不确定因素的影响,需要对这些不确定因素进行管理,以便它们不会干扰已定义的项目目标。在这种情况下,敏捷方法作为一种替代方法出现了,它可以为某些类型的项目带来更好的结果。技术报告显示,成功项目的数量低于预期。其中一个可能的原因是,有许多公司没有应用风险管理或应用不当。在一些公司中,可能需要领导关注组织环境的项目风险管理,即这些风险与几个现有项目的关系。在这种情况下,本文的目标是报告在多个项目环境中实现敏捷风险管理过程的案例研究经验,称为GARA (gest o ágil de Riscos de Ambiente)。一些项目被选中参与这一进程,其目的是对现有障碍进行积极管理,主要是那些影响多个项目的障碍,因为它们的重要性或在这些项目之间共享资源。项目负责人之间的沟通以及他们在解决障碍方面的经验等好处也进行了讨论。