The Change in Boiler and Steam Turbine Failure Modes With Minimum Load Operation: Using Modeling to Predict Susceptibility With Validation Through Plant Testing

T. Reid, J. Malloy, M. Scoffone, S. Reid, A. Fabricius
{"title":"The Change in Boiler and Steam Turbine Failure Modes With Minimum Load Operation: Using Modeling to Predict Susceptibility With Validation Through Plant Testing","authors":"T. Reid, J. Malloy, M. Scoffone, S. Reid, A. Fabricius","doi":"10.1115/power2020-16905","DOIUrl":null,"url":null,"abstract":"\n Reducing the minimum load at which a unit can reliably operate is one method to manage changes in market demands and avoid inherent concerns over frequent on and off cycling. For this reason, it is now becoming common practice for plants to develop new lower minimum load levels that are well below conventional targets provided when the unit was first commissioned. For many plants, the criteria for successful operation were not based on optimizing minimum load levels. In fact, most conventional steam plants were commissioned during an era when full base load operation was expected throughout the life of the plant. Base load availability was the key driver not parameters that promoted unit flexibility. As a result, there are opportunities for plants to lower minimum load levels, but it is important for owners to understand the trade-offs and risks that come with such operation.\n TG Advisers (Turbine - Generator) and Tetra Engineering (Boiler) partnered on an analytical assessment and process simulation for a US site with four vintage boilers and steam turbines, the boilers having been converted from coal to gas-firing some years earlier. The boilers were modeled at different load points using boiler and power plant process simulation software. Key issues analyzed were superheat steam temperature, stability of natural circulation, and maintenance of minimum flow velocities. Secondary factors included cold end condensation and the potential for accumulation of dissolved solids in the circuit.\n Utilizing the results of Tetra’s boiler model, TGA completed off-design modeling and calculations for the steam turbine and balance of plant equipment. Examples of primary interest was the impact of the predicted steam conditions and superheat, resulting thermal transient cycles, and LP blading concerns influenced by moisture content and back pressure control. Finally, balance of plant equipment was reviewed to ensure acceptable operating points for key equipment such as boiler feed pumps, feedwater heaters, and hood spray systems.\n Following computer simulations, a plant testing plan was developed, and plant testing was completed. The paper will review analytical predictions and actual plant testing as well as overall lessons learned from the project. Through these analytical and testing efforts the minimum load was reduced from the current practice of 65 MW to 31 MW.","PeriodicalId":282703,"journal":{"name":"ASME 2020 Power Conference","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-08-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"ASME 2020 Power Conference","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/power2020-16905","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Reducing the minimum load at which a unit can reliably operate is one method to manage changes in market demands and avoid inherent concerns over frequent on and off cycling. For this reason, it is now becoming common practice for plants to develop new lower minimum load levels that are well below conventional targets provided when the unit was first commissioned. For many plants, the criteria for successful operation were not based on optimizing minimum load levels. In fact, most conventional steam plants were commissioned during an era when full base load operation was expected throughout the life of the plant. Base load availability was the key driver not parameters that promoted unit flexibility. As a result, there are opportunities for plants to lower minimum load levels, but it is important for owners to understand the trade-offs and risks that come with such operation. TG Advisers (Turbine - Generator) and Tetra Engineering (Boiler) partnered on an analytical assessment and process simulation for a US site with four vintage boilers and steam turbines, the boilers having been converted from coal to gas-firing some years earlier. The boilers were modeled at different load points using boiler and power plant process simulation software. Key issues analyzed were superheat steam temperature, stability of natural circulation, and maintenance of minimum flow velocities. Secondary factors included cold end condensation and the potential for accumulation of dissolved solids in the circuit. Utilizing the results of Tetra’s boiler model, TGA completed off-design modeling and calculations for the steam turbine and balance of plant equipment. Examples of primary interest was the impact of the predicted steam conditions and superheat, resulting thermal transient cycles, and LP blading concerns influenced by moisture content and back pressure control. Finally, balance of plant equipment was reviewed to ensure acceptable operating points for key equipment such as boiler feed pumps, feedwater heaters, and hood spray systems. Following computer simulations, a plant testing plan was developed, and plant testing was completed. The paper will review analytical predictions and actual plant testing as well as overall lessons learned from the project. Through these analytical and testing efforts the minimum load was reduced from the current practice of 65 MW to 31 MW.
最小负荷运行时锅炉和汽轮机失效模式的变化:利用模型预测敏感性并通过工厂试验验证
降低机组可以可靠运行的最低负荷是管理市场需求变化和避免频繁开关循环固有问题的一种方法。出于这个原因,电厂开发新的更低的最低负荷水平已成为一种普遍做法,远低于机组首次投入使用时提供的常规目标。对于许多电厂来说,成功运行的标准不是基于优化最小负荷水平。事实上,大多数传统的蒸汽电厂都是在整个电厂寿命期间期望全基本负荷运行的时代投入使用的。基本负荷可用性是关键驱动因素,而不是提高机组灵活性的参数。因此,电厂有机会降低最低负荷水平,但重要的是业主要了解这种操作带来的权衡和风险。TG顾问公司(汽轮机-发电机)和利乐工程公司(锅炉)合作,对一个美国工厂进行了分析评估和过程模拟,该工厂有4台老式锅炉和蒸汽轮机,这些锅炉几年前已经从燃煤改为燃气。利用锅炉电厂过程仿真软件对不同负荷点的锅炉进行建模。分析的关键问题是过热蒸汽温度、自然循环的稳定性和保持最小流速。次要因素包括冷端冷凝和在电路中积累溶解固体的潜力。利用Tetra锅炉模型的结果,TGA完成了汽轮机和工厂设备平衡的非设计建模和计算。主要关注的例子是预测蒸汽条件和过热的影响,由此产生的热瞬态循环,以及受水分含量和背压控制影响的低压叶片问题。最后,对工厂设备的平衡进行了审查,以确保锅炉给水泵、给热水器和通风柜喷雾系统等关键设备的可接受工作点。在电脑模拟后,制订了工厂测试计划,并完成了工厂测试。本文将回顾分析预测和实际工厂测试,以及从该项目中吸取的总体经验教训。通过这些分析和测试工作,最小负荷从目前的65兆瓦降低到31兆瓦。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信