{"title":"AWR-26 Topside Reuse Project","authors":"Somsak Boonthieng, Nuntawatt Pairachavet, Witoo Soraphetphisai, Wuttipong Poungthip, Chananwath Sinthumongkhonchai, Charkorn Petcharoen, Puwadon Assadornithee","doi":"10.2523/iptc-22715-ms","DOIUrl":null,"url":null,"abstract":"\n Wellhead Platform AWP-26 was originally developed under PTTEP Arthit Phase 2C, completed installation in 2014 and started a production from 2016 to serve gas plateau and to sustain the Arthit production. Upon depletion of AWP-26 in 2019, PTTEP Arthit Asset realized the opportunity to relocate the AWP-26 to the new prospective location in order to maximize reservoir production. In 2021, the first PTTEP Topside Reuse Project has been put into the offshore execution stage where we proud to present in this paper.\n The main objective of the project is to convert the originally topside design AWP-26 to suit with new prospective location and renamed to AWR-26. The topside is reused where the subsea structure (so called \"jacket\") is newly built as to suit with new water depth and soil parameters at the new location. The existing jacket and subsea pipeline were left as is for future decommissioning. While waiting the existing jacket to be decommissioned, tentative in 2026-2031, it is important to install navigation lights system to warn the marine to avoid collision of the remaining jacket structure. The minimal and fit for purposed structure platform is then designed (so called \"navigation aid platform\") was fabricated and installed onto the existing jacket for safe marine operation.\n It is not so simple just to relocate and make use of the existing topside to suit with the new prospective location, there were tremendous activities to be considered, starting with engineering design to make the existing topside design to be technically compatible with new process parameters of the new prospective location. Following by the early stage for preparatory works in collaboration within an internal PTTEP parties (Project Construction, Arthit Asset, Arthit Operation & Maintenance and Logistic Team), for the activities including but not limited to; platform plug and abandon, removal of flowlines, preservation of Booster Compressor, collecting the base line inspection data for piping system, platform structural integrity check, etc. In addition, to ascertain the overall weight of topside was within the safe margin and clearly defined the Centre of Gravity (CG) for the topside lifting purpose, all the vessels, tanks, containers, associated piping including the sludge removal were performed.","PeriodicalId":283978,"journal":{"name":"Day 1 Wed, March 01, 2023","volume":"10 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-02-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 1 Wed, March 01, 2023","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2523/iptc-22715-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Wellhead Platform AWP-26 was originally developed under PTTEP Arthit Phase 2C, completed installation in 2014 and started a production from 2016 to serve gas plateau and to sustain the Arthit production. Upon depletion of AWP-26 in 2019, PTTEP Arthit Asset realized the opportunity to relocate the AWP-26 to the new prospective location in order to maximize reservoir production. In 2021, the first PTTEP Topside Reuse Project has been put into the offshore execution stage where we proud to present in this paper. The main objective of the project is to convert the originally topside design AWP-26 to suit with new prospective location and renamed to AWR-26. The topside is reused where the subsea structure (so called "jacket") is newly built as to suit with new water depth and soil parameters at the new location. The existing jacket and subsea pipeline were left as is for future decommissioning. While waiting the existing jacket to be decommissioned, tentative in 2026-2031, it is important to install navigation lights system to warn the marine to avoid collision of the remaining jacket structure. The minimal and fit for purposed structure platform is then designed (so called "navigation aid platform") was fabricated and installed onto the existing jacket for safe marine operation. It is not so simple just to relocate and make use of the existing topside to suit with the new prospective location, there were tremendous activities to be considered, starting with engineering design to make the existing topside design to be technically compatible with new process parameters of the new prospective location. Following by the early stage for preparatory works in collaboration within an internal PTTEP parties (Project Construction, Arthit Asset, Arthit Operation & Maintenance and Logistic Team), for the activities including but not limited to; platform plug and abandon, removal of flowlines, preservation of Booster Compressor, collecting the base line inspection data for piping system, platform structural integrity check, etc. In addition, to ascertain the overall weight of topside was within the safe margin and clearly defined the Centre of Gravity (CG) for the topside lifting purpose, all the vessels, tanks, containers, associated piping including the sludge removal were performed.
AWR-26上层甲板再利用项目
AWP-26井口平台最初是在PTTEP Arthit 2C阶段开发的,于2014年完成安装,并从2016年开始生产,以服务天然气平台并维持Arthit的生产。在2019年AWP-26耗尽后,PTTEP Arthit Asset意识到有机会将AWP-26重新安置到新的预期位置,以最大限度地提高油藏产量。2021年,第一个PTTEP上层平台再利用项目已经进入海上执行阶段,我们很自豪地在本文中介绍。该项目的主要目标是改造原来的上层设计AWP-26,以适应新的预期位置,并更名为AWR-26。为了适应新位置的新水深和土壤参数,在新建的海底结构(所谓的“护套”)中,上层结构可以重复使用。现有的导管套和海底管道被保留下来,以备将来退役。在等待现有导管架退役期间(暂定在2026-2031年),安装导航灯系统以警告船员避免剩余导管架结构的碰撞是很重要的。然后设计最小且适合特定结构的平台(即所谓的“导航辅助平台”),并将其制造并安装到现有的导管套上,以确保海上安全操作。搬迁和利用现有的上层平台来适应新的预期位置并不是那么简单,需要考虑的活动很多,从工程设计开始,使现有的上层平台设计在技术上与新的预期位置的新工艺参数兼容。随后,在PTTEP内部各方(项目建设、Arthit资产、Arthit运维和物流团队)的协作下进行前期准备工作,活动包括但不限于;平台的塞弃、管线的拆除、增压压缩机的保存、管道系统基线检查数据的收集、平台结构完整性检查等。此外,为了确保上层甲板的整体重量在安全范围内,并明确界定上层甲板吊装的重心,所有船只、储罐、容器、相关管道,包括污泥清除都进行了测试。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信