M. Swathi Ramesh, S. Smrithi, P. AkhilRajkoti, P. Kanakasabapathy, A. Ravishankar, Soumajit Pal, P. Poornachandran
{"title":"Development of SCADA automated 33kV substation model as testing platform","authors":"M. Swathi Ramesh, S. Smrithi, P. AkhilRajkoti, P. Kanakasabapathy, A. Ravishankar, Soumajit Pal, P. Poornachandran","doi":"10.1109/IIC.2015.7150976","DOIUrl":null,"url":null,"abstract":"This paper discusses construction and testing of a scaled down model of 33 kV substation using SCADA (Supervisory Control And Data Acquisition). The model works as a testing platform for conducting various kinds of automation tests like unscheduled load shedding, time based load shedding, over voltage protection etc. The model provides hands on experience of automation which results in enhancement of control, accuracy, and reliability of the substation. The substation is monitored and controlled using SCADA. The objective of this paper is to demonstrate how to develop an efficient system and using it as a real-world testing platform that enables the collection of right amount of data and relaying it to the controlling utility at right time to take right actions for smooth performance and good efficiency. Also to study the security concerns of the system by modelling the threats associated it.","PeriodicalId":155838,"journal":{"name":"2015 International Conference on Industrial Instrumentation and Control (ICIC)","volume":"7 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2015-05-28","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2015 International Conference on Industrial Instrumentation and Control (ICIC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IIC.2015.7150976","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
Abstract
This paper discusses construction and testing of a scaled down model of 33 kV substation using SCADA (Supervisory Control And Data Acquisition). The model works as a testing platform for conducting various kinds of automation tests like unscheduled load shedding, time based load shedding, over voltage protection etc. The model provides hands on experience of automation which results in enhancement of control, accuracy, and reliability of the substation. The substation is monitored and controlled using SCADA. The objective of this paper is to demonstrate how to develop an efficient system and using it as a real-world testing platform that enables the collection of right amount of data and relaying it to the controlling utility at right time to take right actions for smooth performance and good efficiency. Also to study the security concerns of the system by modelling the threats associated it.
本文讨论了基于SCADA (Supervisory Control and Data Acquisition)的33kv变电站缩尺模型的构建和测试。该模型可作为测试平台进行各种自动化测试,如非计划减载、基于时间的减载、过压保护等。该模型提供了自动化的实践经验,从而提高了变电站的控制、准确性和可靠性。采用SCADA对变电站进行监控。本文的目的是演示如何开发一个有效的系统,并将其用作现实世界的测试平台,该平台能够收集适量的数据,并在正确的时间将其传递给控制实用程序,以采取正确的操作,从而实现平稳的性能和良好的效率。同时,通过建模与系统相关的威胁来研究系统的安全问题。