Modelling construction scheduling constraints using shapes constraint language (SHACL)

Ranjith K. Soman
{"title":"Modelling construction scheduling constraints using shapes constraint language (SHACL)","authors":"Ranjith K. Soman","doi":"10.35490/EC3.2019.170","DOIUrl":null,"url":null,"abstract":"This paper presents a new approach for modelling construction scheduling constraints using Shapes Constraint Language. Current modelling approaches focuses on modelling precedence and discrete constraints at master planning or phase planning level and lacks the ability to model complex constraints at look ahead planning level. Proposed modelling approach addresses this limitation. Precedence constraints, discrete resource capacity constraints, disjunctive constraints and logical constraints are modelled using shapes constraint language for a simple lifting problem in this paper. The modelled constraints were tested, and the constraints model was able to identify the violations effectively and produce a validation report.","PeriodicalId":126601,"journal":{"name":"Proceedings of the 2019 European Conference on Computing in Construction","volume":"1 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-07-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 2019 European Conference on Computing in Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.35490/EC3.2019.170","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

Abstract

This paper presents a new approach for modelling construction scheduling constraints using Shapes Constraint Language. Current modelling approaches focuses on modelling precedence and discrete constraints at master planning or phase planning level and lacks the ability to model complex constraints at look ahead planning level. Proposed modelling approach addresses this limitation. Precedence constraints, discrete resource capacity constraints, disjunctive constraints and logical constraints are modelled using shapes constraint language for a simple lifting problem in this paper. The modelled constraints were tested, and the constraints model was able to identify the violations effectively and produce a validation report.
基于形状约束语言(SHACL)的施工进度约束建模
本文提出了一种利用形状约束语言对施工进度约束进行建模的新方法。目前的建模方法主要集中在总体规划或阶段规划层面上对优先约束和离散约束的建模,缺乏在前瞻性规划层面上对复杂约束的建模能力。提出的建模方法解决了这一限制。本文采用形状约束语言对一个简单的提升问题进行了优先约束、离散资源容量约束、析取约束和逻辑约束的建模。对建模的约束进行了测试,并且约束模型能够有效地识别违例并生成验证报告。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信