An Integrated Approach to Optimise an Offshore Field Development Plan

H. Kasekar, U. Ghauri, M. Nevin, Raphaele Mel, M. Uijttenhout, J. Alblooshi, E. Draoui
{"title":"An Integrated Approach to Optimise an Offshore Field Development Plan","authors":"H. Kasekar, U. Ghauri, M. Nevin, Raphaele Mel, M. Uijttenhout, J. Alblooshi, E. Draoui","doi":"10.2118/202852-ms","DOIUrl":null,"url":null,"abstract":"\n The ADNOC Offshore oilfield located in the Arabian Gulf is being developed utilising various wellhead towers, infield pipelines and a standalone super complex. The field development team devised an updated subsurface plan to achieve production targets beyond the original plan. The incremental oil necessitated assessment of original surface facilities design to identify any bottlenecks and unlock constraints.\n A set of production forecasts were initially provided as basis for assessment covering various scenarios and range of reservoir uncertainties. To manage these uncertainties, the facilities and subsurface development teams worked in an integrated and iterative way. The production profiles were used to assess and develop understanding of surface facilities such as oil flowline network, water injection supply and network, gas lift networks and the major equipment.\n The assessment results provided guidelines on the process facilities constraints which were feedback to subsurface team. An optimised subsurface development plan was then generated respecting the facility constraint and leveraging the existing facilities design to utilise ullages.\n An initial view of investment to produce incremental oil considered installing three new wellhead towers, a new manifold platform and a new water injection platform both linked to the super complex and a new main oil line installation to transfer partially stabilised oil from super complex to oil processing plant. The technical evaluations and the decision analysis resulted in a low-cost solution that was needed to ensure that the field's incremental oil production is economically viable.\n The integrated approach not only allowed selection of techno-commercial robust solution but also allowed optimisation of investment providing flexibility to accommodate the key project uncertainties. This was achieved by deferring the investment to future by descoping the overall development plan in two separate projects - achieve production plateau and sustain plateau. The interim period between the two projects would provide time to resolve the subsurface uncertainties and an opportunity to revisit future development strategy without committing any investment. In addition, the original UTC was significantly improved. This approach emphasised the importance of having a flexible surface facilities solution in accommodating the developments in the subsurface field development strategy especially in an offshore environment and during the early field production period.\n This paper presents an approach followed for optimisation of an offshore oilfield development plan under various surface facilities constraints.","PeriodicalId":357553,"journal":{"name":"Day 2 Tue, November 10, 2020","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2020-11-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, November 10, 2020","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/202852-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The ADNOC Offshore oilfield located in the Arabian Gulf is being developed utilising various wellhead towers, infield pipelines and a standalone super complex. The field development team devised an updated subsurface plan to achieve production targets beyond the original plan. The incremental oil necessitated assessment of original surface facilities design to identify any bottlenecks and unlock constraints. A set of production forecasts were initially provided as basis for assessment covering various scenarios and range of reservoir uncertainties. To manage these uncertainties, the facilities and subsurface development teams worked in an integrated and iterative way. The production profiles were used to assess and develop understanding of surface facilities such as oil flowline network, water injection supply and network, gas lift networks and the major equipment. The assessment results provided guidelines on the process facilities constraints which were feedback to subsurface team. An optimised subsurface development plan was then generated respecting the facility constraint and leveraging the existing facilities design to utilise ullages. An initial view of investment to produce incremental oil considered installing three new wellhead towers, a new manifold platform and a new water injection platform both linked to the super complex and a new main oil line installation to transfer partially stabilised oil from super complex to oil processing plant. The technical evaluations and the decision analysis resulted in a low-cost solution that was needed to ensure that the field's incremental oil production is economically viable. The integrated approach not only allowed selection of techno-commercial robust solution but also allowed optimisation of investment providing flexibility to accommodate the key project uncertainties. This was achieved by deferring the investment to future by descoping the overall development plan in two separate projects - achieve production plateau and sustain plateau. The interim period between the two projects would provide time to resolve the subsurface uncertainties and an opportunity to revisit future development strategy without committing any investment. In addition, the original UTC was significantly improved. This approach emphasised the importance of having a flexible surface facilities solution in accommodating the developments in the subsurface field development strategy especially in an offshore environment and during the early field production period. This paper presents an approach followed for optimisation of an offshore oilfield development plan under various surface facilities constraints.
优化海上油田开发计划的综合方法
位于阿拉伯湾的ADNOC海上油田正在利用各种井口塔、场内管道和一个独立的超级综合设施进行开发。油田开发团队设计了一个更新的地下计划,以实现超出原计划的生产目标。增加的石油需要对原始地面设施设计进行评估,以确定任何瓶颈并解除限制。最初提供了一套产量预测作为评估的基础,涵盖了各种情景和油藏不确定性范围。为了管理这些不确定性,设施和地下开发团队以集成和迭代的方式工作。生产剖面用于评估和了解地面设施,如油流网络、注水供应和网络、气举网络和主要设备。评估结果提供了有关工艺设施限制的指导方针,并将其反馈给地下团队。然后,根据设施限制和利用现有设施设计来利用村庄,生成了优化的地下开发计划。为了增加石油产量,最初的投资考虑了安装三个新的井口塔、一个新的歧管平台和一个新的注水平台,这两个平台都与超级综合设施相连,并安装了一条新的主要输油管道,将部分稳定的石油从超级综合设施输送到石油加工厂。技术评估和决策分析得出了一种低成本的解决方案,以确保该油田的增产在经济上是可行的。综合方法不仅允许选择技术-商业健壮的解决方案,还允许优化投资,提供灵活性,以适应关键项目的不确定性。这是通过将投资推迟到未来,将整体开发计划划分为两个独立的项目来实现的——实现生产平稳期和维持平稳期。两个项目之间的过渡时期将为解决地下不确定性提供时间,并有机会在不进行任何投资的情况下重新审视未来的开发战略。另外,原来的UTC也得到了很大的改进。这种方法强调了灵活的地面设施解决方案的重要性,以适应地下油田开发战略的发展,特别是在海上环境和油田早期生产阶段。本文提出了在各种地面设施约束条件下海上油田开发方案优化的一种方法。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信