Heuristics and applications for resource-constrained project scheduling with minimal and maximal time lags

J. Corner, L. Foulds, K. Neumann
{"title":"Heuristics and applications for resource-constrained project scheduling with minimal and maximal time lags","authors":"J. Corner, L. Foulds, K. Neumann","doi":"10.1109/INES.1997.632452","DOIUrl":null,"url":null,"abstract":"Projects with minimal and maximal time lags between different activities are considered. We model such projects using cyclic activity-on-node networks. Heuristics for various types of optimization problems are discussed. The problem of finding an optimal make-to order production schedule is modelled as a resource-constrained project scheduling problem. We outline what appear to be fruitful areas of further research into certain issues in this field. We conclude that the newly developed models and solution techniques represent useful advances in project scheduling.","PeriodicalId":161975,"journal":{"name":"Proceedings of IEEE International Conference on Intelligent Engineering Systems","volume":"22 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1997-09-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of IEEE International Conference on Intelligent Engineering Systems","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/INES.1997.632452","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Projects with minimal and maximal time lags between different activities are considered. We model such projects using cyclic activity-on-node networks. Heuristics for various types of optimization problems are discussed. The problem of finding an optimal make-to order production schedule is modelled as a resource-constrained project scheduling problem. We outline what appear to be fruitful areas of further research into certain issues in this field. We conclude that the newly developed models and solution techniques represent useful advances in project scheduling.
具有最小和最大时间滞后的资源约束项目调度的启发式方法及其应用
考虑不同活动之间最小和最大时间滞后的项目。我们使用节点上循环活动网络对这类项目进行建模。讨论了各种类型优化问题的启发式方法。将寻找最优按订单生产计划的问题建模为资源受限的项目调度问题。我们概述了对这一领域的某些问题进行进一步研究的似乎富有成果的领域。我们得出结论,新开发的模型和解决方案技术代表了项目调度的有用进展。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信