Analisis Kinerja Alat Berat Pada Proyek Normalisasi dan Perkuatan Tebing Sungai

Ansar Jaya, Irwan Lakawa, Sitti Hawa, Muh Samtun Bona
{"title":"Analisis Kinerja Alat Berat Pada Proyek Normalisasi dan Perkuatan Tebing Sungai","authors":"Ansar Jaya, Irwan Lakawa, Sitti Hawa, Muh Samtun Bona","doi":"10.54297/sciej.v3i1.239","DOIUrl":null,"url":null,"abstract":"The purpose of this study was to analyze the performance of heavy equipment and the duration of time required to complete the Windo River Cliff Normalization and Reinforcement Project, Pamandati Village, Laeya District, South Konawe Regency. The results showed that the excavator's performance in excavation work (mechanical) was 38.68 m3/hour, dump truck 2.99 m3/hour. As for the embankment work imported from outside, the performance of the excavator is 98.53 m3/hour and the dump truck is 3.05 m3/hour. Where the duration of time required to complete the excavation work (mechanical) with an excavator is 12 days and for embankment work imported from outside is 2 days..","PeriodicalId":275633,"journal":{"name":"Sultra Civil Engineering Journal","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2022-06-27","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Sultra Civil Engineering Journal","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.54297/sciej.v3i1.239","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The purpose of this study was to analyze the performance of heavy equipment and the duration of time required to complete the Windo River Cliff Normalization and Reinforcement Project, Pamandati Village, Laeya District, South Konawe Regency. The results showed that the excavator's performance in excavation work (mechanical) was 38.68 m3/hour, dump truck 2.99 m3/hour. As for the embankment work imported from outside, the performance of the excavator is 98.53 m3/hour and the dump truck is 3.05 m3/hour. Where the duration of time required to complete the excavation work (mechanical) with an excavator is 12 days and for embankment work imported from outside is 2 days..
分析河崖正常化和冲击项目中的重型机械性能
本研究的目的是分析重型设备的性能和完成Windo河悬崖规范和加固项目所需的时间,Pamandati村,Laeya区,南科纳威县。结果表明,挖掘机在开挖工作(机械)中的性能为38.68 m3/h,自卸车为2.99 m3/h。对于外部进口的路堤工作,挖掘机性能为98.53 m3/小时,自卸车性能为3.05 m3/小时。用挖掘机完成挖掘(机械)工作所需时间为12天,从外部进口的路堤工作所需时间为2天。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信