An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects

P. Balducci, L. Schienbein, T. Nguyen, D. Brown, E. Fathelrahman
{"title":"An examination of the costs and critical characteristics of electric utility distribution system capacity enhancement projects","authors":"P. Balducci, L. Schienbein, T. Nguyen, D. Brown, E. Fathelrahman","doi":"10.1109/TDC.2006.1668461","DOIUrl":null,"url":null,"abstract":"Summary form only given. This paper classifies and analyzes the capital and total costs for 172 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities in the Western United States. Projects were sorted into eight categories: capacitors, bad transfer, new feeder, new line, new substation, new transformer, reconductoring, and substation capacity increase. Capital cost and total cost frequency distributions were constructed along with descriptive statistics for each project type. Ordinary least squares (OLS) regression analysis was performed to determine how various project variables (e.g., project location and primary customer served by the project) impact the unit costs. Distribution system capital costs averaged $51/kVA of additional capacity and varied significantly by project type. New substations and new transformers were the most costly, $112/kVA and $87/kVA respectively, while reconductoring and substation capacity increase were found to be the least expensive ($21/kVA). Using the full costs of delivering electricity over the 30-year life of a project increased the mean project cost to $100/kVA. The OLS analysis revealed that the primary determinant of total project cost is project type. Other variables, such as the geographic location of the project and primary customer served, did not yield statistically significant results.","PeriodicalId":308184,"journal":{"name":"IEEE PES Power Systems Conference and Exposition, 2004.","volume":"34 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2006-05-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"16","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"IEEE PES Power Systems Conference and Exposition, 2004.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/TDC.2006.1668461","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 16

Abstract

Summary form only given. This paper classifies and analyzes the capital and total costs for 172 electricity distribution system capacity enhancement projects undertaken during 1995-2002 or planned in the 2003-2011 time period by three electric power utilities in the Western United States. Projects were sorted into eight categories: capacitors, bad transfer, new feeder, new line, new substation, new transformer, reconductoring, and substation capacity increase. Capital cost and total cost frequency distributions were constructed along with descriptive statistics for each project type. Ordinary least squares (OLS) regression analysis was performed to determine how various project variables (e.g., project location and primary customer served by the project) impact the unit costs. Distribution system capital costs averaged $51/kVA of additional capacity and varied significantly by project type. New substations and new transformers were the most costly, $112/kVA and $87/kVA respectively, while reconductoring and substation capacity increase were found to be the least expensive ($21/kVA). Using the full costs of delivering electricity over the 30-year life of a project increased the mean project cost to $100/kVA. The OLS analysis revealed that the primary determinant of total project cost is project type. Other variables, such as the geographic location of the project and primary customer served, did not yield statistically significant results.
电力公用事业配电系统容量增强项目的成本和关键特征的研究
只提供摘要形式。本文对美国西部三家电力公司在1995-2002年或2003-2011年期间进行或计划进行的172个配电系统容量提升项目的资金和总成本进行了分类和分析。项目分为电容器、坏传输、新馈线、新线路、新变电站、新变压器、重导和变电站容量增加八类。为每个项目类型构建了资本成本和总成本频率分布以及描述性统计数据。执行普通最小二乘(OLS)回归分析来确定各种项目变量(例如,项目位置和项目服务的主要客户)如何影响单位成本。配电系统的资本成本平均为51美元/千伏安的额外容量,并因项目类型而有很大差异。新建变电站和新建变压器的成本最高,分别为112美元/千伏安和87美元/千伏安,而重导和增加变电站容量的成本最低(21美元/千伏安)。在一个项目30年的生命周期内,使用全部的电力成本将项目的平均成本提高到100美元/千伏安。OLS分析表明,项目总成本的主要决定因素是项目类型。其他变量,如项目的地理位置和所服务的主要客户,并没有产生统计上显著的结果。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信