{"title":"Buffer Sizing Methods to Compare Critical Chain Project Management with Critical Path","authors":"M. Shurrab, G. Abbasi","doi":"10.4018/IJITPM.2016070105","DOIUrl":null,"url":null,"abstract":"Critical Chain Project Management CCPM provided a tangible progress to the Project Management Body of Knowledge. The critical chain project management CCPM differs from the traditional Critical Path Method CPM which includes never changing resource dependencies. CCPM improves the project plan by aggregating uncertainty into buffers at the end of activity paths. In this research, one hundred twenty random projects were generated and analyzed using Microsoft Project software according to the traditional CPM and the CCPM once using the sum of squares SSQ method and another using the cut & past C&PM method. CCPM-SSQ method revealed an average savings of 13% and 43% in duration and cost, with a standard deviation of 21 and 11 for duration and cost respectively. While the CCPM-C&PM method revealed an average overestimation of about 2% in duration and 43% savings in cost, with a standard deviation of 25 and 11 for duration and cost respectively.","PeriodicalId":375999,"journal":{"name":"Int. J. Inf. Technol. Proj. Manag.","volume":"20 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Int. J. Inf. Technol. Proj. Manag.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4018/IJITPM.2016070105","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3
Abstract
Critical Chain Project Management CCPM provided a tangible progress to the Project Management Body of Knowledge. The critical chain project management CCPM differs from the traditional Critical Path Method CPM which includes never changing resource dependencies. CCPM improves the project plan by aggregating uncertainty into buffers at the end of activity paths. In this research, one hundred twenty random projects were generated and analyzed using Microsoft Project software according to the traditional CPM and the CCPM once using the sum of squares SSQ method and another using the cut & past C&PM method. CCPM-SSQ method revealed an average savings of 13% and 43% in duration and cost, with a standard deviation of 21 and 11 for duration and cost respectively. While the CCPM-C&PM method revealed an average overestimation of about 2% in duration and 43% savings in cost, with a standard deviation of 25 and 11 for duration and cost respectively.
关键链项目管理CCPM为项目管理知识体系提供了切实的进展。关键链项目管理(CCPM)不同于传统的关键路径方法(CPM),后者包括不改变资源依赖关系。CCPM通过将不确定性聚合到活动路径末端的缓冲中来改进项目计划。在本研究中,根据传统CPM和CCPM分别采用平方和SSQ法和cut & past C&PM法生成120个随机项目,并利用Microsoft Project软件对其进行分析。CCPM-SSQ方法在工期和成本上平均节省13%和43%,工期和成本的标准差分别为21和11。而CCPM-C&PM方法显示,平均高估了约2%的持续时间,节省了43%的成本,持续时间和成本的标准差分别为25和11。