Performance study of Micro-hydropower system in Nepal

S. Khadka, R. Maskey
{"title":"Performance study of Micro-hydropower system in Nepal","authors":"S. Khadka, R. Maskey","doi":"10.1109/ICSET.2012.6357409","DOIUrl":null,"url":null,"abstract":"This study focuses on the performance study of the Micro-Hydropower Plant (MHP), upto 100 kW, system in terms of the overall efficiency, that is, water- to- wire efficiency. MHP has been playing a significant role for electrification of the remote rural areas of the Nepal. Generally, 50 % overall efficiency is adopted while designing the MHP without consideration of the sizes of the plants due to the lack of testing facilities of such domestically made turbine before installation. The field test was conducted, in each individual powerhouse, using additional dump load (ADL) method. In this method, the consumer load and Electronic Load Controller (ELC) were disconnected and terminals of the ADL were connected to generator. During the testing ADL was switched on 1 kW interval and the discharge was controlled through the gate valve by maintaining frequency of 50 Hz. The corresponding discharge was recorded along with net head, current and voltage. Then the flow versus overall efficiency of the plant gives the maximum water to wire efficiency of the plant at a given discharge.","PeriodicalId":256740,"journal":{"name":"2012 IEEE Third International Conference on Sustainable Energy Technologies (ICSET)","volume":"22 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2012-11-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"8","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2012 IEEE Third International Conference on Sustainable Energy Technologies (ICSET)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICSET.2012.6357409","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 8

Abstract

This study focuses on the performance study of the Micro-Hydropower Plant (MHP), upto 100 kW, system in terms of the overall efficiency, that is, water- to- wire efficiency. MHP has been playing a significant role for electrification of the remote rural areas of the Nepal. Generally, 50 % overall efficiency is adopted while designing the MHP without consideration of the sizes of the plants due to the lack of testing facilities of such domestically made turbine before installation. The field test was conducted, in each individual powerhouse, using additional dump load (ADL) method. In this method, the consumer load and Electronic Load Controller (ELC) were disconnected and terminals of the ADL were connected to generator. During the testing ADL was switched on 1 kW interval and the discharge was controlled through the gate valve by maintaining frequency of 50 Hz. The corresponding discharge was recorded along with net head, current and voltage. Then the flow versus overall efficiency of the plant gives the maximum water to wire efficiency of the plant at a given discharge.
尼泊尔微型水电系统性能研究
本研究主要针对100千瓦以下的微型水电厂(MHP)系统的整体效率,即水到线效率进行性能研究。MHP一直在尼泊尔偏远农村地区的电气化方面发挥着重要作用。由于国产水轮机在安装前缺乏试验设施,在设计中一般采用50%的总效率,不考虑电厂的规模。采用附加倾卸负荷(ADL)法,在每个厂房进行了现场试验。该方法将用户负荷与电子负荷控制器(ELC)断开,将ADL端子与发电机连接。在测试过程中,ADL开关间隔为1kw,通过闸阀控制放电,保持频率为50hz。记录相应的放电情况,同时记录净头、电流和电压。然后,流量相对于工厂的整体效率给出了在给定流量下工厂的最大水到线效率。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信